1237 N EDGEMONT ST 1-50 90029
Certificate Information: 1237 N EDGEMONT ST 1-50 90029
- Application / Permit
- 20016-20000-14737
- Plan Check / Job No.
- B20VN08288
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT THE (E) LAUNDRY ROOM/ STORAGE AREA AT BASEMENT TO ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(C) AND (N) MECHANICAL ROOM.
- Permit Issued
- Issued on 3/16/2021
- Issuing Office
- Current Status
- CofO Issued on 6/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2020 | ALYSSA N NARCISO |
| Corrections Issued | 7/1/2020 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 7/29/2020 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 8/21/2020 | LUIS RINCON |
| Plan Check Approved | 10/21/2020 | LUIS RINCON |
| Plan Check Approved | 3/15/2021 | SERGIO MUNIZ |
| Issued | 3/16/2021 | APPLICANT |
| Building Plans Picked Up | 6/16/2021 | APPLICANT |
| CofO in Progress | 6/25/2025 | LUIS CCAMACHO |
| Permit Finaled | 6/25/2025 | ERNESTO CORRAL |
| CofO Issued | 6/25/2025 | ERNESTO CORRAL |
| Permit Finaled | 6/25/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 7/9/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 7/10/2020 | CECILIO NAVARRO |
| Tenant Habitability Plan | Cleared | 7/10/2020 | STEVEN HOFSTAD |
| Specific Plan | Cleared | 3/15/2021 | DANALYNN DOMINGUEZ |
Contact Information
| Contractor | Retrofitting360 Inc; Lic. No.: 1039226-B | 19562 VENTURA BLVD# 230 TARZANA, CA 91356 |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 21201 KITTRIDGE ST APT 9105 WOODLAND HILLS, CA 91303 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/13/2021 | Approved | RUSSELL BONVOULOIR |
| Wood Frame | 4/13/2021 | Partial Inspection | RUSSELL BONVOULOIR |
| Deputy Drilled-In Anchors | 4/22/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Reinf. Concrete | 4/22/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 4/22/2021 | Approved | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 4/22/2021 | Approved | RUSSELL BONVOULOIR |
| Green Building Rough | 6/30/2021 | Approved | JONATHAN QUACH |
| Reinforced Concrete Frame | 6/30/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Structural Steel Frame | 6/30/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Wood Frame | 6/30/2021 | Partial Approval | JONATHAN QUACH |
| Insulation | 7/8/2021 | Approved | TIMOTHY BUXTON |
| Reinforced Concrete Frame | 7/9/2021 | No Access for Inspection | JONATHAN QUACH |
| Structural Steel Frame | 7/9/2021 | No Access for Inspection | JONATHAN QUACH |
| Wood Frame | 7/9/2021 | No Access for Inspection | JONATHAN QUACH |
| Drywall Nailing | 7/27/2021 | Approved | LANNY MERRICK |
| Green Building Final | 12/28/2021 | Partial Inspection | SORIN CIRSTOIU |
| Wood Frame | 12/28/2021 | Corrections Issued | SORIN CIRSTOIU |
| Wood Frame | 12/29/2021 | Partial Inspection | JONATHAN QUACH |
| Drywall Nailing | 1/27/2022 | Approved | JONATHAN QUACH |
| Wood Frame | 1/27/2022 | Approved | JONATHAN QUACH |
| Final | 6/21/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Green Building Final | 6/21/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Reinforced Concrete Frame | 6/21/2022 | Not Ready for Inspection | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 6/21/2022 | SGSOV Not Ready | JONATHAN QUACH |
| Smoke Detectors | 6/21/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Final | 2/21/2023 | Not Ready for Inspection | RONALD JIMENEZ |
| Green Building Final | 2/21/2023 | Approved | RONALD JIMENEZ |
| Reinforced Concrete Frame | 2/21/2023 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 2/21/2023 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 2/21/2023 | Not Ready for Inspection | RONALD JIMENEZ |
| Final | 3/9/2023 | Not Ready for Inspection | RONALD JIMENEZ |
| Smoke Detectors | 3/9/2023 | Approved | RONALD JIMENEZ |
| Final | 1/22/2024 | No Access for Inspection | RAFAEL CORTES |
| Final | 2/1/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 5/13/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Final | 6/10/2025 | OK to Issue CofO | LUIS CCAMACHO |
| Final | 6/24/2025 | Not Ready for Inspection | JAMES POWERS |