15719-15721 W DRELL ST 91342
Certificate Information: 15719-15721 W DRELL ST 91342
- Application / Permit
- 20016-20000-14379
- Plan Check / Job No.
- B20VN08124
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) 18'-9" x 20' ATT. GARAGE INTO A (N) ACCESSORY DWELLING UNIT GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/6/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/19/2020 | PINANK PATEL |
| Corrections Issued | 6/22/2020 | PINANK PATEL |
| Applicant returned to address corrections | 5/25/2022 | PINANK PATEL |
| Building Plans Picked Up | 5/31/2022 | APPLICANT |
| Issued | 9/6/2022 | APPLICANT |
| CofO in Progress | 12/1/2025 | KEVIN BERBERYAN |
| CofO Issued | 12/18/2025 | RUBEN SALAS |
| Permit Finaled | 12/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/8/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 10/8/2020 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 3/30/2021 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/12/2023 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/14/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 5/1/2023 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 5/1/2023 | Approved | ARAM AVEDISIAN |
| Sewer | 5/1/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 5/15/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 5/22/2024 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 5/22/2024 | Approved | KEVIN BERBERYAN |
| Insulation | 8/12/2024 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 10/8/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 6/16/2025 | Approved | KEVIN BERBERYAN |
| Final | 6/16/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 6/16/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Rough | 6/16/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 6/16/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 6/16/2025 | Approved | KEVIN BERBERYAN |
| Service/Power Release | 6/23/2025 | Approved | KEVIN BERBERYAN |
| Final | 11/7/2025 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 11/7/2025 | Approved | KEVIN BERBERYAN |