1661 N MCCOLLUM ST 90026

Certificate Information: 1661 N MCCOLLUM ST 90026

Application / Permit
20016-20000-14336
Plan Check / Job No.
B20VN08096
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL THE (E) ATTACHED CARPORT TO CONVERT THE ROOF TO A (N) DECK. EXTEND EXISTING STAIRWAY.
Permit Issued
Issued on 4/21/2021
Issuing Office
Current Status
Permit Finaled on 9/13/2021

Permit Application Status History

Submitted 6/17/2020 APPLICANT
Assigned to Plan Check Engineer 6/20/2020 SARKIS HARABEDIAN
Corrections Issued 6/20/2020 SARKIS HARABEDIAN
Building Plans Picked Up 6/25/2020 APPLICANT
Applicant returned to address corrections 7/20/2020 SARKIS HARABEDIAN
Applicant returned to address corrections 8/26/2020 JENNIFER LEE
Plan Check Approved 9/15/2020 SARKIS HARABEDIAN
No Progress 9/15/2020 SARKIS HARABEDIAN
Plan Check Approved 9/17/2020 SARKIS HARABEDIAN
Issued 4/21/2021 APPLICANT
Permit Finaled 9/13/2021 THOMAS LOGRASSO

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/31/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 8/4/2020 CECILIO NAVARRO
Grading Pre-Inspection Cleared 9/15/2020 SARKIS HARABEDIAN

Contact Information

Contractor La-Decks; Lic. No.: 968237-B 10880 WILSHSIRE BLVD 1101      LOS ANGELES, CA 90024
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/6/2021 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 5/14/2021 Corrections Issued ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 5/28/2021 Not Ready for Inspection RUBEN SALAS
Footing/Foundation/Slab 5/28/2021 Not Ready for Inspection RUBEN SALAS
Footing/Foundation/Slab 6/8/2021 Approved SCOTT FINNILA
BUILDING-Rough-Frame 7/1/2021 Approved HAMIK HARTOUNIAN
Final 8/13/2021 Corrections Issued THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 8/13/2021 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 8/13/2021 Approved THOMAS LOGRASSO
Final 8/18/2021 Not Ready for Inspection THOMAS LOGRASSO
Final 8/24/2021 Not Ready for Inspection THOMAS LOGRASSO
Final 9/1/2021 Corrections Issued CRAIG DAVIS
Final 9/13/2021 Permit Finaled THOMAS LOGRASSO