1152 1/2-1/4 E 33RD ST 90011

Certificate Information: 1152 1/2-1/4 E 33RD ST 90011

Application / Permit
20016-20000-14332
Plan Check / Job No.
B20VN08095
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ECPC: CONVERT THE (E) 31' X 22' THREE CAR GARAGE INTO A (N) ACCESSORY DWELLING UNIT ON FIRST FLOOR OF (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING
Permit Issued
Issued on 7/29/2020
Issuing Office
Current Status
CofO Issued on 7/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/17/2020 APPLICANT
Assigned to Plan Check Engineer 6/19/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 6/19/2020 SEWADA ZADOORIAN MILAGARDI
Building Plans Picked Up 6/25/2020 APPLICANT
Plan Check Approved 7/29/2020 SEWADA ZADOORAN MILAGARDI
Issued 7/29/2020 APPLICANT
CofO in Progress 7/30/2021 HORACE FULTZ
Permit Finaled 7/30/2021 DEROLD HAUFF
CofO Issued 7/30/2021 DEROLD HAUFF
Permit Finaled 7/30/2021 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 7/13/2020 PHILLIP MUNGUIA
Address approval Cleared 7/17/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 7/17/2020 CECILIO NAVARRO
Sewer availability Cleared 7/17/2020 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/14/2020 Partial Approval ROBERT MCDOWELL
Sewer 8/14/2020 Approved ROBERT MCDOWELL
Underground Mechanical 8/14/2020 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 8/20/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 8/20/2020 Approved ROBERT MCDOWELL
Green Building Rough 8/20/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 8/20/2020 Approved ROBERT MCDOWELL
Drywall Nailing 8/25/2020 Not Ready for Inspection DAVID MATSON
Drywall Nailing 8/27/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 8/27/2020 Approved SABAS ALONSO
Shower Pan 8/27/2020 Approved SABAS ALONSO
ELECTRICAL-Final 10/6/2020 Approved ROBERT MCDOWELL
Final 10/6/2020 Corrections Issued ROBERT MCDOWELL
Green Building Final 10/6/2020 Approved ROBERT MCDOWELL
HVAC-Final 10/6/2020 Approved ROBERT MCDOWELL
PLUMBING-Final 10/6/2020 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 10/6/2020 SGSOV Approved ROBERT MCDOWELL
Smoke Detectors 10/6/2020 Approved ROBERT MCDOWELL
Final 11/16/2020 Corrections Issued ROBERT MCDOWELL
Final 7/30/2021 OK to Issue CofO HORACE FULTZ