6544-6546 N BOBBYBOYAR AVE 91307

Certificate Information: 6544-6546 N BOBBYBOYAR AVE 91307

Application / Permit
20016-20000-14099
Plan Check / Job No.
B20VN07973
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING ATTACHED GARAGE TO NEW ACCESSORY DWELLING UNIT
Permit Issued
Issued on 8/28/2020
Issuing Office
Current Status
CofO Issued on 7/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2020 APPLICANT
Assigned to Plan Check Engineer 6/16/2020 SELLA BENYAMIN
Corrections Issued 6/17/2020 SELLA BENYAMIN
Building Plans Picked Up 6/19/2020 APPLICANT
Plan Check Approved 7/27/2020 SELLA BENYAMIN
Issued 8/28/2020 APPLICANT
CofO in Progress 7/5/2021 TROY SANDERS
CofO Issued 7/20/2021 JOHN JANSON
Permit Finaled 7/20/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/24/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 6/24/2020 GABRIEL ROBLES
Sewer availability Cleared 6/24/2020 GABRIEL ROBLES
Hold Cleared 12/1/2020 JASON SHEETS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/4/2020 Not Ready for Inspection TROY SANDERS
PLUMBING-Rough 12/4/2020 Partial Approval TROY SANDERS
Sewer 12/4/2020 Approved TROY SANDERS
Footing/Foundation/Slab 12/9/2020 Approved TROY SANDERS
ELECTRICAL-Rough 1/5/2021 Not Ready for Inspection TROY SANDERS
HVAC-Rough 1/5/2021 Approved TROY SANDERS
Interior/Exterior Lathing 1/5/2021 Not Ready for Inspection TROY SANDERS
PLUMBING-Rough 1/5/2021 Approved TROY SANDERS
Shower Pan 1/5/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 1/11/2021 Approved TROY SANDERS
Green Building Rough 1/11/2021 Approved TROY SANDERS
Interior/Exterior Lathing 1/11/2021 Approved TROY SANDERS
Rough-Elec/Plmb/HVAC 1/11/2021 Approved TROY SANDERS
Drywall Nailing 1/21/2021 Approved TROY SANDERS
Final 6/17/2021 No Access for Inspection DAVID SCANTLIN
Green Building Final 6/17/2021 No Access for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 6/17/2021 SGSOV Not Ready DAVID SCANTLIN
Smoke Detectors 6/17/2021 No Access for Inspection DAVID SCANTLIN
Final 6/24/2021 Corrections Issued TROY SANDERS
Green Building Final 6/24/2021 Corrections Issued TROY SANDERS
SGSOV-Seismic Gas S/O Valve 6/24/2021 SGSOV Approved TROY SANDERS
Smoke Detectors 6/24/2021 Approved TROY SANDERS
ELECTRICAL-Final 7/2/2021 Approved TROY SANDERS
Final 7/2/2021 OK to Issue CofO TROY SANDERS
Green Building Final 7/2/2021 Approved TROY SANDERS
HVAC-Final 7/2/2021 Approved TROY SANDERS
PLUMBING-Final 7/2/2021 Approved TROY SANDERS