819 S CLOVERDALE AVE 90036

Certificate Information: 819 S CLOVERDALE AVE 90036

Application / Permit
20016-20000-14041
Plan Check / Job No.
B20VN07941
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE 19' X 20' (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISION.
Permit Issued
Issued on 7/30/2020
Issuing Office
Current Status
CofO Issued on 1/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2020 APPLICANT
Assigned to Plan Check Engineer 6/16/2020 SERGIO MUNIZ
Corrections Issued 6/17/2020 SERGIO MUNIZ
Building Plans Picked Up 6/19/2020 APPLICANT
Plan Check Approved 7/30/2020 SERGIO MUNIZ
Issued 7/30/2020 APPLICANT
CofO in Progress 1/20/2021 CHRIS CHRISTENSEN
Permit Finaled 1/23/2021 DEROLD HAUFF
CofO Issued 1/23/2021 DEROLD HAUFF
Permit Finaled 1/23/2021 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 6/22/2020 GABRIEL ROBLES
Address approval Cleared 7/8/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/8/2020 WALLIE JONG
HPOZ Cleared 7/16/2020 CHRISTINA PARK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/13/2020 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 8/17/2020 Partial Approval ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 8/21/2020 Approved ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 8/27/2020 Corrections Issued COREY HUPP
Excavation/Setback/Form/Re-Bar 9/3/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 9/22/2020 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Rough 9/22/2020 Approved CHRIS CHRISTENSEN
Wood Frame 9/22/2020 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/6/2020 Approved ARTHUR SARGSYAN
Insulation 10/13/2020 Approved ARTHUR SARGSYAN
Drywall Nailing 10/23/2020 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 10/23/2020 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 1/6/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 1/6/2021 Corrections Issued CHRIS CHRISTENSEN
Final 1/6/2021 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 1/6/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 1/6/2021 Approved CHRIS CHRISTENSEN
HVAC-Final 1/6/2021 Approved CHRIS CHRISTENSEN
METHANE-Final 1/6/2021 Approved CHRIS CHRISTENSEN
METHANE-Rough 1/6/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 1/6/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 1/6/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 1/6/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 1/19/2021 Approved CHRIS CHRISTENSEN
Final 1/19/2021 OK to Issue CofO CHRIS CHRISTENSEN