5749 W VALLEY OAK DR 90068
Certificate Information: 5749 W VALLEY OAK DR 90068
- Application / Permit
- 20016-20000-14033
- Plan Check / Job No.
- B20VN07934
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR KITCHEN REMODEL, REMOVE WALLS AND ADD NEW BEAM/POSTS PER ENGINEERING DESIGN
- Permit Issued
- Issued on 9/15/2020
- Issuing Office
- Current Status
- Permit Finaled on 5/5/2021
Permit Application Status History
| Submitted | 6/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2020 | JEFFREY TANGONAN |
| Corrections Issued | 6/15/2020 | JEFFREY TANGONAN |
| Issued | 9/15/2020 | APPLICANT |
| Permit Finaled | 5/5/2021 | BRIAN SULLIVAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 6/18/2020 | LAUREN PADICK |
| Grading Pre-Inspection | Cleared | 7/8/2020 | BRIAN MILLER |
Contact Information
| Contractor | Pro Touch Construction Group; Lic. No.: 1054974-B | 17547 VENTURA BLVD #307A ENCINO, CA 91316 |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/8/2020 | Conditional Approval | ROBERT CORNELL |
| Footing/Foundation/Slab | 10/14/2020 | Approved | BRIAN SULLIVAN |
| Wood Frame | 10/14/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 11/5/2020 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 11/5/2020 | Approved | BRIAN SULLIVAN |
| Wood Frame | 11/5/2020 | Partial Inspection | BRIAN SULLIVAN |
| Drywall Nailing | 11/18/2020 | Approved | BRIAN SULLIVAN |
| Insulation | 11/18/2020 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 12/11/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 12/16/2020 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 4/12/2021 | SGSOV Not Ready | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 4/23/2021 | SGSOV Not Ready | BRIAN SULLIVAN |
| Final | 5/5/2021 | Permit Finaled | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 5/5/2021 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 5/5/2021 | Approved | BRIAN SULLIVAN |