1619 S HIGHLAND AVE 90019

Certificate Information: 1619 S HIGHLAND AVE 90019

Application / Permit
20016-20000-13876
Plan Check / Job No.
B20VN07863
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE (E) 2'-1" X 13'-6" AND 2'-2" X 21'-7" PORTIONS OF (E) CARPORT; CONVERT 13'-11" X 18'-3" PORTION OF (E) CARPORT, CONVERT (E) 20'-4" X 20'-5" DETACHED GARAGE AND ADD 12'-2" X 27'-3" FOR NEW ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(C) AND (D). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/18/2021
Issuing Office
Current Status
CofO Issued on 10/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2020 APPLICANT
Assigned to Plan Check Engineer 6/12/2020 JENNIFER LEE
Corrections Issued 6/17/2020 JENNIFER LEE
Plan Check Approved 2/19/2021 JENNIFER LEE
Building Plans Picked Up 2/25/2021 APPLICANT
Issued 3/18/2021 APPLICANT
CofO in Progress 8/29/2022 JOSE AVILA
Permit Finaled 10/1/2022 DEROLD HAUFF
CofO Issued 10/1/2022 DEROLD HAUFF
Permit Finaled 10/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/30/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/30/2020 WALLIE JONG
Sewer availability Cleared 6/30/2020 WALLIE JONG
Construction near power lines Cleared 9/22/2020 RIDWAN HARDY
Construction within easement Cleared 9/22/2020 RIDWAN HARDY
Low Impact Development Cleared 1/6/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 2/3/2021 WALLIE JONG

Contact Information

Contractor Vision Contractor; Lic. No.: 1064662-B 2056 S HARVARD BLVD APT 6      LOS ANGELES, CA 90018
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/3/2021 Partial Approval KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 7/1/2021 Corrections Issued JOSEPH MCGARRY
METHANE-Subgrade 7/1/2021 Approved JOSEPH MCGARRY
PLUMBING-Rough 7/1/2021 Partial Approval JOSEPH MCGARRY
Sewer 7/1/2021 Approved JOSEPH MCGARRY
Footing/Foundation/Slab 9/1/2021 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 9/14/2021 Not Ready for Inspection THOMAS LOGRASSO
METHANE-Barrier 9/14/2021 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 9/29/2021 Conditional Approval SCOTT FINNILA
Footing/Foundation/Slab 10/20/2021 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 12/7/2021 Corrections Issued JOSE AVILA
Special/Order Compliance 1/10/2022 No Violation (special insp) AMY COLIN
Special/Order Compliance 2/1/2022 Approved MICHAEL LEWIS
ELECTRICAL-Rough 2/15/2022 Corrections Issued JOSE AVILA
Green Building Rough 2/15/2022 Corrections Issued JOSE AVILA
HVAC-Rough 2/15/2022 Corrections Issued JOSE AVILA
METHANE-Rough 2/15/2022 Approved JOSE AVILA
PLUMBING-Rough 2/15/2022 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 2/22/2022 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 3/1/2022 Partial Approval JOSE AVILA
ELECTRICAL-Rough 3/1/2022 Approved JOSE AVILA
HVAC-Rough 3/1/2022 Partial Approval JOSE AVILA
PLUMBING-Rough 3/1/2022 Approved JOSE AVILA
Insulation 3/8/2022 Approved JOSE AVILA
Interior/Exterior Lathing 3/8/2022 Approved JOSE AVILA
Drywall Nailing 3/24/2022 Partial Approval JOSE AVILA
Green Building Rough 3/24/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 6/27/2022 Approved JOSE AVILA
Drywall Nailing 6/27/2022 Approved JOSE AVILA
ELECTRICAL-Final 6/27/2022 Corrections Issued JOSE AVILA
Green Building Final 6/27/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 6/27/2022 SGSOV Not Ready JOSE AVILA
Smoke Detectors 6/27/2022 Corrections Issued JOSE AVILA
Final 7/12/2022 Corrections Issued JOSE AVILA
Green Building Final 7/12/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 7/12/2022 SGSOV Approved JOSE AVILA
Smoke Detectors 7/12/2022 Approved JOSE AVILA
Final 7/19/2022 Corrections Issued JOSE AVILA
Final 8/26/2022 OK to Issue CofO JOSE AVILA
Service/Power Release 9/12/2022 Approved JOSE AVILA