3045 W LEEWARD AVE 90005

Certificate Information: 3045 W LEEWARD AVE 90005

Application / Permit
20016-20000-13859
Plan Check / Job No.
B20VN07855
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
FIRE DAMAGED REPAIR LESS THAN 20% - ROOF FRAMING, STAIRWAY; REMOVE AND REPLACE INTERIOR DOORS; DRYWALL REPAIR AND ADD INSULATION
Permit Issued
Issued on 1/5/2021
Issuing Office
Current Status
Permit Finaled on 3/18/2025

Permit Application Status History

Submitted 6/18/2020 APPLICANT
Assigned to Plan Check Engineer 7/9/2020 SELLA BENYAMIN
Corrections Issued 7/15/2020 SELLA BENYAMIN
Quality Review Completed 7/17/2020 STEVEN KIM
Building Plans Picked Up 7/21/2020 APPLICANT
Plan Check Approved 12/4/2020 SELLA BENYAMIN
Issued 1/5/2021 APPLICANT
Permit Finaled 3/17/2025 JEROME BLACKWOOD

Permit Application Clearance Information

Redevelopment Project Area Cleared 10/14/2020 DAVID URITA
Fire Marshall Fire Life Safety Cleared 11/23/2020 RONILO MULAWIN

Contact Information

Contractor Macias F Construction Inc; Lic. No.: 913811-B 16007 LEADWELL STREET      VAN NUYS, CA 91406
Engineer Kennedy,, Thomas James; Lic. No.: C74144 5105 E LOS ANGELES AVE 207      SIMI VALLEY, CA 93063

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/12/2021 Approved RUSSELL BONVOULOIR
Pre-Inspection 2/19/2021 Approved RUSSELL BONVOULOIR
Wood Frame 2/19/2021 Partial Approval RUSSELL BONVOULOIR
Pre-Inspection 3/3/2021 Corrections Issued ERNESTO CORRAL
Footing/Foundation/Slab 3/11/2021 Not Ready for Inspection RONALD PACHECO
Wood Frame 3/11/2021 Not Ready for Inspection RONALD PACHECO
Interior/Exterior Lathing 4/19/2021 Approved DANIEL COLLINS
Pre-Inspection 10/7/2021 Corrections Issued TIMOTHY BUXTON
Insulation 4/6/2022 Not Ready for Inspection TIMOTHY BUXTON
Interior/Exterior Lathing 4/6/2022 Not Ready for Inspection TIMOTHY BUXTON
Wood Frame 4/6/2022 Approved TIMOTHY BUXTON
Insulation 4/15/2022 Approved TIMOTHY BUXTON
Drywall Nailing 5/2/2022 Approved TIMOTHY BUXTON
Insulation 5/2/2022 Approved TIMOTHY BUXTON
Final 11/3/2022 Partial Approval TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 11/3/2022 SGSOV Approved TIMOTHY BUXTON
Smoke Detectors 11/3/2022 Approved TIMOTHY BUXTON
Final 5/13/2024 Not Ready for Inspection JEROME BLACKWOOD
Pre-Inspection 5/13/2024 Not Ready for Inspection JEROME BLACKWOOD
Final 2/18/2025 Partial Approval JEROME BLACKWOOD
Final 3/17/2025 Permit Finaled JEROME BLACKWOOD