1844 S LONGWOOD AVE 90019
Certificate Information: 1844 S LONGWOOD AVE 90019
- Application / Permit
- 20016-20000-13770
- Plan Check / Job No.
- B20VN07812
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE AND REC ROOM INTO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 7/23/2020
- Issuing Office
- Current Status
- CofO Issued on 7/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 6/14/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 7/23/2020 | JEROME MAGAT PALMA |
| Issued | 7/23/2020 | APPLICANT |
| CofO in Progress | 4/9/2021 | STUART CHAPMAN |
| Permit Finaled | 7/23/2022 | DEROLD HAUFF |
| CofO Issued | 7/23/2022 | DEROLD HAUFF |
| Permit Finaled | 7/23/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2020 | JEANIE LAM |
| Sewer availability | Cleared | 7/14/2020 | JEANIE LAM |
Contact Information
| Contractor | J G Builders Inc; Lic. No.: 1049536-B | 4418 LA MADERA AVENUE EL MONTE, CA 91732 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/26/2020 | Approved | STUART CHAPMAN |
| Sewer | 12/8/2020 | Partial Approval | STUART CHAPMAN |
| Underground Mechanical | 12/8/2020 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 12/15/2020 | Corrections Issued | STUART CHAPMAN |
| Sewer | 12/15/2020 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 12/24/2020 | Approved | STUART CHAPMAN |
| Sewer | 12/24/2020 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 1/22/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 1/22/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 1/22/2021 | Approved | STUART CHAPMAN |
| METHANE-Rough | 1/22/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 1/22/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 1/27/2021 | Partial Approval | ROBERT VORHIS |
| Insulation | 1/29/2021 | Approved | STUART CHAPMAN |
| Drywall Nailing | 2/1/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 2/1/2021 | Approved | STUART CHAPMAN |
| Final | 3/9/2021 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 3/9/2021 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 3/9/2021 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 3/9/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 4/8/2021 | Approved | STUART CHAPMAN |
| Final | 4/8/2021 | OK to Issue CofO | STUART CHAPMAN |
| Green Building Final | 4/8/2021 | Approved | STUART CHAPMAN |
| HVAC-Final | 4/8/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 4/8/2021 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 4/8/2021 | SGSOV Approved | STUART CHAPMAN |