1815-1815 1/2 N WILTON PL 90028

Certificate Information: 1815-1815 1/2 N WILTON PL 90028

Application / Permit
20016-20000-13732
Plan Check / Job No.
B20VN07801
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT PORTION FAMILY ROOM AND BEDROOM ON FIRST FLOOR OF THE (E) SINGLE FAMILY DWELLING INTO A (N) JR. ACCESSORY DWELLING UNIT (480 SF) AND CREATE A NEW BATHROOM ON SECOND FLOOR ALL WORK PER WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 12/30/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 11/10/2020
Issuing Office
Current Status
CofO Issued on 12/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2020 APPLICANT
Assigned to Plan Check Engineer 6/11/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 6/11/2020 SEWADA ZADOORIAN MILAGARDI
No Progress 6/12/2020 SEWADA ZADOORAN MILAGARDI
Building Plans Picked Up 6/16/2020 APPLICANT
Plan Check Approved 8/14/2020 RAPHAEL ROSAS
No Progress 9/12/2020 RARES BODEA
Issued 11/10/2020 APPLICANT
CofO in Progress 12/1/2022 ROBERT CHAVEZ
CofO in Progress 12/1/2022 ROBERT CHAVEZ
CofO Issued 12/28/2022 DANIEL SANCHEZ
Permit Finaled 12/28/2022 DANIEL SANCHEZ

Permit Application Clearance Information

Miscellaneous Cleared 7/1/2020 DANALYNN DOMINGUEZ
Address approval Cleared 7/2/2020 ELAINE LEI
Sewer availability Cleared 7/2/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 7/6/2020 ELAINE LEI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RUBEN PEREZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT NILES, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
MARK BEVELAQUA, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL SANCHEZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
COREY HUPP, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
EMIL OPFFER, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/18/2021 Approved TIMOTHY MCCURDY
ELECTRICAL-Rough 6/28/2021 Corrections Issued TIMOTHY MCCURDY
Gas Test 6/28/2021 Partial Approval TIMOTHY MCCURDY
HVAC-Rough 6/28/2021 Corrections Issued TIMOTHY MCCURDY
PLUMBING-Rough 6/28/2021 Approved TIMOTHY MCCURDY
Sewer 6/28/2021 Approved TIMOTHY MCCURDY
Wood Frame 6/28/2021 Approved TIMOTHY MCCURDY
BUILDING-Rough-Frame 7/7/2021 Approved TIMOTHY MCCURDY
ELECTRICAL-Rough 7/7/2021 Approved TIMOTHY MCCURDY
Green Building Rough 7/7/2021 Approved TIMOTHY MCCURDY
Interior/Exterior Lathing 7/7/2021 Approved TIMOTHY MCCURDY
MERV13>=Rough 7/7/2021 Approved TIMOTHY MCCURDY
Shower Pan 7/7/2021 Approved TIMOTHY MCCURDY
Wood Frame 7/7/2021 Approved TIMOTHY MCCURDY
Insulation 8/9/2021 Approved ALFREDO BALANDRA
PLUMBING-Rough 10/25/2021 Corrections Issued ALFREDO BALANDRA
Pre-Inspection 3/31/2022 Partial Approval ALFREDO BALANDRA
ELECTRICAL-Rough 5/9/2022 Partial Inspection ALFREDO BALANDRA
PLUMBING-Rough 5/9/2022 Partial Inspection ALFREDO BALANDRA
Underground Mechanical 5/9/2022 Partial Inspection ALFREDO BALANDRA
Wood Frame 5/25/2022 Not Ready for Inspection ALFREDO BALANDRA
Drywall Nailing 6/13/2022 Approved ALFREDO BALANDRA
Shower Pan 7/8/2022 Not Ready for Inspection PIERRE VEGA
Interior/Exterior Lathing 8/5/2022 Approved PIERRE VEGA
Final 9/30/2022 Corrections Issued ROBERT CHAVEZ
Green Building Final 9/30/2022 Not Ready for Inspection ROBERT CHAVEZ
MERV13>=Final 9/30/2022 Approved ROBERT CHAVEZ
SGSOV-Seismic Gas S/O Valve 9/30/2022 SGSOV Approved ROBERT CHAVEZ
Smoke Detectors 9/30/2022 Corrections Issued ROBERT CHAVEZ
Final 10/4/2022 OK to Issue CofO ROBERT CHAVEZ
Gas Test 10/4/2022 Approved ROBERT CHAVEZ
Green Building Final 10/4/2022 Approved ROBERT CHAVEZ
Smoke Detectors 10/4/2022 Approved ROBERT CHAVEZ