4707 N NORWICH AVE 91403

Certificate Information: 4707 N NORWICH AVE 91403

Application / Permit
20016-20000-13542
Plan Check / Job No.
B20VN07738
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 20' X 20' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 9/29/2020
Issuing Office
Current Status
CofO Issued on 8/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2020 APPLICANT
Assigned to Plan Check Engineer 6/16/2020 RAPHAEL ROSAS
Corrections Issued 6/16/2020 RAPHAEL ROSAS
Plan Check Approved 9/18/2020 RAPHAEL ROSAS
Issued 9/29/2020 APPLICANT
CofO in Progress 7/20/2021 ARTHUR SARGSYAN
CofO in Progress 7/20/2021 ARTHUR SARGSYAN
CofO Issued 8/3/2021 MICHAEL SMITH
Permit Finaled 8/3/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/21/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 7/21/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 7/21/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 7/21/2020 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 8/22/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/1/2020 Not Ready for Inspection CHARLES POWELL
ELECTRICAL-Rough 12/1/2020 Partial Approval CHARLES POWELL
Green Building Rough 12/1/2020 Not Ready for Inspection CHARLES POWELL
PLUMBING-Rough 12/1/2020 Approved CHARLES POWELL
ELECTRICAL-Rough 12/8/2020 Approved CHARLES POWELL
Footing/Foundation/Slab 12/8/2020 Approved CHARLES POWELL
BUILDING-Rough-Frame 12/31/2020 Approved CHARLES POWELL
Green Building Rough 12/31/2020 Not Ready for Inspection CHARLES POWELL
Insulation 1/5/2021 Partial Approval CHARLES POWELL
BUILDING-Rough-Frame 1/12/2021 Approved DANIEL ORRANTE
Green Building Final 1/12/2021 Not Ready for Inspection DANIEL ORRANTE
Green Building Rough 1/12/2021 Approved DANIEL ORRANTE
Insulation 1/12/2021 Approved DANIEL ORRANTE
SGSOV-Seismic Gas S/O Valve 1/12/2021 SGSOV Not Ready DANIEL ORRANTE
Smoke Detectors 1/12/2021 Not Ready for Inspection DANIEL ORRANTE
Drywall Nailing 1/22/2021 Approved CHARLES POWELL
Shower Pan 1/22/2021 Approved CHARLES POWELL
Final 5/19/2021 Not Ready for Inspection CHARLES POWELL
Green Building Final 5/19/2021 Not Ready for Inspection CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 5/19/2021 SGSOV Not Ready CHARLES POWELL
Smoke Detectors 5/19/2021 Not Ready for Inspection CHARLES POWELL
Final 7/8/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Final 7/8/2021 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 7/8/2021 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 7/8/2021 Approved CHRISTOPHE COCHRAN
Final 7/15/2021 OK to Issue CofO ARTHUR SARGSYAN