9307 W CATTARAUGUS AVE 90034

Certificate Information: 9307 W CATTARAUGUS AVE 90034

Application / Permit
20016-20000-13269
Plan Check / Job No.
B20VN07594
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT18'-6" X 20'-3" (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT. ALL WORK PER WFPP.
Permit Issued
Issued on 7/10/2020
Issuing Office
Current Status
CofO Issued on 7/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2020 APPLICANT
Assigned to Plan Check Engineer 6/10/2020 SEAN SHAHMIRI
Corrections Issued 6/11/2020 SEAN SHAHMIRI
Building Plans Picked Up 6/16/2020 APPLICANT
Plan Check Approved 7/10/2020 RAPHAEL ROSAS
Issued 7/10/2020 APPLICANT
CofO in Progress 3/23/2021 KEVIN SARGSYAN
Permit Finaled 7/6/2022 DANIEL ORRANTE
CofO Issued 7/6/2022 DANIEL ORRANTE
Permit Finaled 7/6/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/29/2020 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 6/30/2020 CATHERINE ADROVER
Sewer availability Cleared 6/30/2020 CATHERINE ADROVER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/12/2020 Partial Approval KEVIN SARGSYAN
Sewer 8/12/2020 Approved KEVIN SARGSYAN
Deputy Drilled-In Anchors 8/17/2020 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 8/19/2020 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 8/21/2020 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 9/17/2020 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 9/17/2020 Partial Approval KEVIN SARGSYAN
Green Building Rough 9/17/2020 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 9/17/2020 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 9/23/2020 Approved KEVIN SARGSYAN
HVAC-Rough 9/23/2020 Approved KEVIN SARGSYAN
Insulation 9/23/2020 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 9/23/2020 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 9/28/2020 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/28/2020 Approved KEVIN SARGSYAN
Green Building Rough 9/28/2020 Approved KEVIN SARGSYAN
Insulation 9/28/2020 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 9/28/2020 Partial Approval KEVIN SARGSYAN
Drywall Nailing 9/30/2020 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 9/30/2020 Not Ready for Inspection KEVIN SARGSYAN
Interior/Exterior Lathing 10/7/2020 Approved KEVIN SARGSYAN
Shower Pan 10/7/2020 Approved KEVIN SARGSYAN
ELECTRICAL-Final 12/11/2020 Approved KEVIN SARGSYAN
PLUMBING-Final 12/11/2020 Corrections Issued KEVIN SARGSYAN
Final 2/18/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 2/18/2021 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Final 2/18/2021 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Final 2/18/2021 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 2/18/2021 SGSOV Not Ready OGANES TARAKHCHYAN
Service/Power Release 2/18/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Smoke Detectors 2/18/2021 Approved OGANES TARAKHCHYAN
Final 2/25/2021 Corrections Issued KEVIN SARGSYAN
Green Building Final 2/25/2021 Approved KEVIN SARGSYAN
HVAC-Final 2/25/2021 Approved KEVIN SARGSYAN
PLUMBING-Final 2/25/2021 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 2/25/2021 SGSOV Approved KEVIN SARGSYAN
ELECTRICAL-Final 3/23/2021 Approved KEVIN SARGSYAN
Final 3/23/2021 OK to Issue CofO KEVIN SARGSYAN
PLUMBING-Final 3/23/2021 Approved KEVIN SARGSYAN