4069 S TIVOLI AVE 90066
Certificate Information: 4069 S TIVOLI AVE 90066
- Application / Permit
- 20016-20000-13212
- Plan Check / Job No.
- B20VN07559
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 10/17/2020
- Issuing Office
- Current Status
- CofO Issued on 8/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2020 | MARVEL DELACRUZ |
| Corrections Issued | 6/19/2020 | MARVEL DELACRUZ |
| Building Plans Picked Up | 6/30/2020 | APPLICANT |
| Applicant returned to address corrections | 10/9/2020 | ANGELICA DAVE |
| Plan Check Approved | 10/9/2020 | ANGELICA MARTINEZ |
| Issued | 10/17/2020 | APPLICANT |
| CofO in Progress | 8/22/2022 | DAVID FEILER |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
| CofO Issued | 8/25/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZI | Cleared | 7/29/2020 | MIGUEL GAMBOA |
| Address approval | Cleared | 8/3/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 8/3/2020 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2020 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 10/9/2020 | PEDRO AYALA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/10/2020 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 1/22/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 1/22/2021 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 1/22/2021 | Approved | ENRIQUE MIRELES |
| Wood Frame | 1/22/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 1/27/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 2/1/2021 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 2/1/2021 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 2/4/2021 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 2/9/2021 | Not Ready for Inspection | MATT KELLERMAN |
| ELECTRICAL-Final | 2/9/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Final | 2/9/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Green Building Final | 2/9/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Rough-Elec/Plmb/HVAC | 2/9/2021 | Not Ready for Inspection | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 2/9/2021 | SGSOV Not Ready | MATT KELLERMAN |
| Smoke Detectors | 2/9/2021 | Not Ready for Inspection | MATT KELLERMAN |
| ELECTRICAL-Final | 2/22/2021 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 2/26/2021 | Approved | ENRIQUE MIRELES |
| Green Building Final | 2/26/2021 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 2/26/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 2/26/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 2/26/2021 | Approved | ENRIQUE MIRELES |
| Final | 7/7/2022 | Corrections Issued | PATRICK QUALEY |
| Final | 8/22/2022 | OK to Issue CofO | DAVID FEILER |