6945-6947 N COMANCHE AVE 91306

Certificate Information: 6945-6947 N COMANCHE AVE 91306

Application / Permit
20016-20000-13199
Plan Check / Job No.
B20VN07552
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ECPC: CONVERT (E) 370SF GARAGE TO A (N) ACCESSORY DWELLING UNIT AND ENCLOSE (E) 85SF COVERED PATIO TO A LAUNDRY ROOM.
Permit Issued
Issued on 6/29/2020
Issuing Office
Current Status
CofO Issued on 3/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2020 APPLICANT
Assigned to Plan Check Engineer 6/10/2020 DAWN MC NULTY
Corrections Issued 6/16/2020 DAWN MC NULTY
Building Plans Picked Up 6/18/2020 APPLICANT
Plan Check Approved 6/29/2020 LUIS RINCON
Issued 6/29/2020 APPLICANT
CofO in Progress 1/7/2021 HENRY KIM
Permit Finaled 3/1/2021 JOHN JANSON
CofO Issued 3/1/2021 JOHN JANSON
Permit Finaled 3/1/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/18/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/18/2020 ADRIAN CASTRO
Permit Cleared 6/18/2020 ADRIAN CASTRO
Sewer availability Cleared 6/18/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/24/2020 Corrections Issued HENRY KIM
Footing/Foundation/Slab 8/3/2020 Approved HENRY KIM
PLUMBING-Rough 8/3/2020 Partial Approval HENRY KIM
BUILDING-Rough-Frame 8/11/2020 Corrections Issued HENRY KIM
ELECTRICAL-Rough 8/11/2020 Corrections Issued HENRY KIM
PLUMBING-Rough 8/11/2020 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 9/1/2020 Not Ready for Inspection HENRY KIM
ELECTRICAL-Rough 9/1/2020 Approved HENRY KIM
HVAC-Rough 9/1/2020 Approved HENRY KIM
PLUMBING-Rough 9/1/2020 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/4/2020 Partial Approval HENRY KIM
PLUMBING-Rough 9/4/2020 Partial Approval HENRY KIM
BUILDING-Rough-Frame 9/17/2020 Partial Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/17/2020 Partial Approval HENRY KIM
Insulation 9/17/2020 Partial Approval HENRY KIM
Interior/Exterior Lathing 9/17/2020 Approved HENRY KIM
PLUMBING-Rough 9/17/2020 Approved HENRY KIM
BUILDING-Rough-Frame 9/23/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/23/2020 Approved HENRY KIM
Green Building Rough 9/23/2020 Approved HENRY KIM
Insulation 9/23/2020 Approved HENRY KIM
Drywall Nailing 9/25/2020 Approved HENRY KIM
Interior/Exterior Lathing 10/5/2020 Approved HENRY KIM
Sewer 10/5/2020 Approved HENRY KIM
Shower Pan 10/5/2020 Approved HENRY KIM
ELECTRICAL-Final 12/8/2020 Corrections Issued HENRY KIM
Final 12/8/2020 Corrections Issued HENRY KIM
Green Building Final 12/8/2020 Approved HENRY KIM
HVAC-Final 12/8/2020 Corrections Issued HENRY KIM
PLUMBING-Final 12/8/2020 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 12/8/2020 SGSOV Approved HENRY KIM
Smoke Detectors 12/8/2020 Approved HENRY KIM
Final 12/29/2020 Not Ready for Inspection HENRY KIM
ELECTRICAL-Final 1/7/2021 Approved HENRY KIM
Final 1/7/2021 OK to Issue CofO HENRY KIM
HVAC-Final 1/7/2021 Approved HENRY KIM
PLUMBING-Final 1/7/2021 Approved HENRY KIM