846-848 1/2 E 85TH ST 90001
Certificate Information: 846-848 1/2 E 85TH ST 90001
- Application / Permit
- 20016-20000-13194
- Plan Check / Job No.
- B20VN07550
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT PORTION OF (E) 3- CAR GARAGE INTO A (N) ACCESSORY DWELLING UNIT AT FIRST FLOOR. ATTACHED DUPLEX AND 1 CAR GARAGE TO REMAIN PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 7/16/2021
- Issuing Office
- Current Status
- CofO Corrected on 6/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2020 | ALYSSA N NARCISO |
| Corrections Issued | 6/17/2020 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 3/4/2021 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 4/16/2021 | APPLICANT |
| Plan Check Approved | 7/16/2021 | MOHAMMAD ESMAILI |
| Issued | 7/16/2021 | APPLICANT |
| CofO in Progress | 2/20/2024 | MICHAEL LEWIS |
| CofO Issued-Status Void | 2/22/2024 | DEROLD HAUFF |
| Permit Finaled-Status Void | 2/22/2024 | DEROLD HAUFF |
| Re-Activate Permit | 4/23/2024 | DEROLD HAUFF |
| CofO Corrected | 6/3/2024 | DEROLD HAUFF |
| Permit Finaled | 6/3/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/30/2020 | JEANIE LAM |
| Sewer availability | Cleared | 7/30/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2020 | JEANIE LAM |
| Construction near power lines | Cleared | 12/12/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/12/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/1/2022 | Partial Inspection | LILIANA PORTILLO |
| Pre-Inspection | 3/1/2023 | Partial Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 5/3/2023 | Approved | MICHAEL LEWIS |
| Grounding or Bonding | 5/23/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 5/23/2023 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/29/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Rough | 6/29/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| Footing/Foundation/Slab | 6/29/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 6/29/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| PLUMBING-Rough | 6/29/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 7/6/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Rough | 7/6/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 7/6/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| HVAC-Rough | 7/14/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 7/18/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 7/18/2023 | Partial Inspection | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 7/18/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| Insulation | 7/20/2023 | Conditional Approval | MICHAEL LEWIS |
| Drywall Nailing | 7/25/2023 | Not Ready for Inspection | DONALD CRICHLOW |
| Drywall Nailing | 7/26/2023 | Approved | DONALD CRICHLOW |
| BUILDING-Rough-Frame | 9/28/2023 | No Access for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Final | 9/28/2023 | No Access for Inspection | MICHAEL LEWIS |
| Final | 9/28/2023 | No Access for Inspection | MICHAEL LEWIS |
| Green Building Final | 9/28/2023 | No Access for Inspection | MICHAEL LEWIS |
| Green Building Rough | 9/28/2023 | No Access for Inspection | MICHAEL LEWIS |
| HVAC-Final | 9/28/2023 | No Access for Inspection | MICHAEL LEWIS |
| PLUMBING-Final | 9/28/2023 | No Access for Inspection | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 9/28/2023 | SGSOV Not Ready | MICHAEL LEWIS |
| Smoke Detectors | 9/28/2023 | No Access for Inspection | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 10/5/2023 | SGSOV Not Ready | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 12/18/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 12/18/2023 | Corrections Issued | MICHAEL LEWIS |
| Final | 12/18/2023 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 12/18/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 12/18/2023 | Approved | MICHAEL LEWIS |
| HVAC-Final | 12/18/2023 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 12/18/2023 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 12/18/2023 | SGSOV Not Ready | MICHAEL LEWIS |
| Smoke Detectors | 12/18/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 12/18/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 1/4/2024 | SGSOV Not Ready | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 1/16/2024 | SGSOV Not Ready | MICHAEL LEWIS |
| ELECTRICAL-Final | 1/30/2024 | Approved | MICHAEL LEWIS |
| Final | 1/30/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 1/30/2024 | Partial Inspection | MICHAEL LEWIS |
| PLUMBING-Final | 1/30/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 1/30/2024 | SGSOV Approved | MICHAEL LEWIS |
| Final | 2/15/2024 | OK to Issue CofO | MICHAEL LEWIS |