846-848 1/2 E 85TH ST 90001

Certificate Information: 846-848 1/2 E 85TH ST 90001

Application / Permit
20016-20000-13194
Plan Check / Job No.
B20VN07550
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT PORTION OF (E) 3- CAR GARAGE INTO A (N) ACCESSORY DWELLING UNIT AT FIRST FLOOR. ATTACHED DUPLEX AND 1 CAR GARAGE TO REMAIN PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 7/16/2021
Issuing Office
Current Status
CofO Corrected on 6/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2020 APPLICANT
Assigned to Plan Check Engineer 6/10/2020 ALYSSA N NARCISO
Corrections Issued 6/17/2020 ALYSSA N NARCISO
Applicant returned to address corrections 3/4/2021 MOHAMMAD ESMAILI
Building Plans Picked Up 4/16/2021 APPLICANT
Plan Check Approved 7/16/2021 MOHAMMAD ESMAILI
Issued 7/16/2021 APPLICANT
CofO in Progress 2/20/2024 MICHAEL LEWIS
CofO Issued-Status Void 2/22/2024 DEROLD HAUFF
Permit Finaled-Status Void 2/22/2024 DEROLD HAUFF
Re-Activate Permit 4/23/2024 DEROLD HAUFF
CofO Corrected 6/3/2024 DEROLD HAUFF
Permit Finaled 6/3/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/30/2020 JEANIE LAM
Sewer availability Cleared 7/30/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/4/2020 JEANIE LAM
Construction near power lines Cleared 12/12/2020 RIDWAN HARDY
Construction within easement Cleared 12/12/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/1/2022 Partial Inspection LILIANA PORTILLO
Pre-Inspection 3/1/2023 Partial Inspection LILIANA PORTILLO
Footing/Foundation/Slab 5/3/2023 Approved MICHAEL LEWIS
Grounding or Bonding 5/23/2023 Not Ready for Inspection JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 5/23/2023 Corrections Issued JOSEPH MCGARRY
BUILDING-Rough-Frame 6/29/2023 Not Ready for Inspection MICHAEL LEWIS
ELECTRICAL-Rough 6/29/2023 Not Ready for Inspection MICHAEL LEWIS
Footing/Foundation/Slab 6/29/2023 Approved MICHAEL LEWIS
Green Building Rough 6/29/2023 Not Ready for Inspection MICHAEL LEWIS
PLUMBING-Rough 6/29/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 7/6/2023 Not Ready for Inspection MICHAEL LEWIS
ELECTRICAL-Rough 7/6/2023 Approved MICHAEL LEWIS
Green Building Rough 7/6/2023 Not Ready for Inspection MICHAEL LEWIS
HVAC-Rough 7/14/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 7/18/2023 Approved MICHAEL LEWIS
ELECTRICAL-Rough 7/18/2023 Partial Inspection MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 7/18/2023 Approved MICHAEL LEWIS
Green Building Rough 7/18/2023 Not Ready for Inspection MICHAEL LEWIS
Insulation 7/20/2023 Conditional Approval MICHAEL LEWIS
Drywall Nailing 7/25/2023 Not Ready for Inspection DONALD CRICHLOW
Drywall Nailing 7/26/2023 Approved DONALD CRICHLOW
BUILDING-Rough-Frame 9/28/2023 No Access for Inspection MICHAEL LEWIS
ELECTRICAL-Final 9/28/2023 No Access for Inspection MICHAEL LEWIS
Final 9/28/2023 No Access for Inspection MICHAEL LEWIS
Green Building Final 9/28/2023 No Access for Inspection MICHAEL LEWIS
Green Building Rough 9/28/2023 No Access for Inspection MICHAEL LEWIS
HVAC-Final 9/28/2023 No Access for Inspection MICHAEL LEWIS
PLUMBING-Final 9/28/2023 No Access for Inspection MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 9/28/2023 SGSOV Not Ready MICHAEL LEWIS
Smoke Detectors 9/28/2023 No Access for Inspection MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 10/5/2023 SGSOV Not Ready MICHAEL LEWIS
BUILDING-Rough-Frame 12/18/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 12/18/2023 Corrections Issued MICHAEL LEWIS
Final 12/18/2023 Corrections Issued MICHAEL LEWIS
Green Building Final 12/18/2023 Approved MICHAEL LEWIS
Green Building Rough 12/18/2023 Approved MICHAEL LEWIS
HVAC-Final 12/18/2023 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 12/18/2023 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 12/18/2023 SGSOV Not Ready MICHAEL LEWIS
Smoke Detectors 12/18/2023 Approved MICHAEL LEWIS
Underground Mechanical 12/18/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 1/4/2024 SGSOV Not Ready RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 1/16/2024 SGSOV Not Ready MICHAEL LEWIS
ELECTRICAL-Final 1/30/2024 Approved MICHAEL LEWIS
Final 1/30/2024 Corrections Issued MICHAEL LEWIS
HVAC-Final 1/30/2024 Partial Inspection MICHAEL LEWIS
PLUMBING-Final 1/30/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 1/30/2024 SGSOV Approved MICHAEL LEWIS
Final 2/15/2024 OK to Issue CofO MICHAEL LEWIS