3906 W BOYCE AVE 90039
Certificate Information: 3906 W BOYCE AVE 90039
- Application / Permit
- 20016-20000-13085
- Plan Check / Job No.
- B20VN07475
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 7/31/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/4/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2020 | SEAN SHAHMIRI |
| Building Plans Picked Up | 6/16/2020 | APPLICANT |
| Corrections Issued | 6/17/2020 | SEAN SHAHMIRI |
| Plan Check Approved | 7/14/2020 | JEROME MAGAT PALMA |
| Issued | 7/31/2020 | APPLICANT |
| CofO in Progress | 11/2/2020 | HAMIK HARTOUNIAN |
| Permit Finaled | 11/4/2020 | DEROLD HAUFF |
| CofO Issued | 11/4/2020 | DEROLD HAUFF |
| Permit Finaled | 11/4/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/23/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 6/23/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2020 | EMIL KYUPELYAN |
| ZI | Cleared | 7/6/2020 | VINCENT QUITORIANO |
Contact Information
| No Data Available. |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/10/2020 | Approved | HAMIK HARTOUNIAN |
| Sewer | 8/10/2020 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 8/10/2020 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/20/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/20/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Wood Frame | 8/20/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Insulation | 8/27/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 8/27/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 9/1/2020 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 9/1/2020 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/1/2020 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 9/1/2020 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/9/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Final | 10/9/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 10/9/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 10/9/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 10/9/2020 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 10/9/2020 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/2/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 11/2/2020 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 11/2/2020 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 11/2/2020 | Approved | HAMIK HARTOUNIAN |