8950-8952 N GOTHIC AVE 91343
Certificate Information: 8950-8952 N GOTHIC AVE 91343
- Application / Permit
- 20016-20000-13044
- Plan Check / Job No.
- B20VN07448
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) ATTACHED TWO CAR GARAGE INTO A (N) JR. ACCESSORY DWELLING UNIT. ALL WORK PER WFPP.
- Permit Issued
- Issued on 10/9/2020
- Issuing Office
- Current Status
- CofO Issued on 4/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2020 | SEAN SHAHMIRI |
| Building Plans Picked Up | 6/16/2020 | APPLICANT |
| Corrections Issued | 6/17/2020 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 9/1/2020 | ALFRED RAMIREZ |
| Plan Check Approved | 9/15/2020 | ALFRED RAMIREZ |
| Issued | 10/9/2020 | APPLICANT |
| CofO in Progress | 1/5/2021 | ARTHUR SARGSYAN |
| CofO in Progress | 1/5/2021 | ARTHUR SARGSYAN |
| No Progress | 3/2/2021 | JACK KARGODORIAN |
| CofO in Progress | 3/12/2021 | JACK KARGODORIAN |
| Permit Finaled | 4/24/2021 | MICHAEL SMITH |
| CofO Issued | 4/24/2021 | MICHAEL SMITH |
| Permit Finaled | 4/24/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/21/2020 | GABRIEL ROBLES |
| Address approval | Cleared | 7/22/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Resolution Design Inc; Lic. No.: 893709-B | P O BOX 1482 SANTA CLARITA, CA 91386 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/30/2020 | Approved | CHARLES POWELL |
| PLUMBING-Rough | 10/30/2020 | Partial Approval | CHARLES POWELL |
| ELECTRICAL-Rough | 11/9/2020 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 11/9/2020 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 11/9/2020 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 11/9/2020 | Partial Approval | ARTHUR SARGSYAN |
| Insulation | 11/10/2020 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2020 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 11/20/2020 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 11/20/2020 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 12/30/2020 | Approved | ARTHUR SARGSYAN |
| Final | 12/30/2020 | Corrections Issued | ARTHUR SARGSYAN |
| Green Building Final | 12/30/2020 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 12/30/2020 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 12/30/2020 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 12/30/2020 | Approved | ARTHUR SARGSYAN |
| Final | 1/4/2021 | OK to Issue CofO | ARTHUR SARGSYAN |
| Special/Order Compliance | 3/15/2021 | Corrections Issued | ARTHUR SARGSYAN |
| Pre-Inspection | 4/21/2021 | Approved | MICHAEL TEMPLE |