17603-17605 W TULSA ST 91344
Certificate Information: 17603-17605 W TULSA ST 91344
- Application / Permit
- 20016-20000-13038
- Plan Check / Job No.
- B20VN07446
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) 20'-1" X 25'-2" TWO CAR GARAGE INTO A (N) ACCESSORY DWELLING UNIT, AND CONVERT THE (E) BREEZWAY TO LIVING AREA AND INTERIOR REMODEL ALL WORK PER WFPP
- Permit Issued
- Issued on 7/20/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/3/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 6/9/2020 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 6/10/2020 | APPLICANT |
| Plan Check Approved | 7/13/2020 | RAPHAEL ROSAS |
| Issued | 7/20/2020 | APPLICANT |
| CofO in Progress | 12/2/2020 | DAVID SCANTLIN |
| Permit Finaled | 12/3/2020 | JOHN JANSON |
| CofO Issued | 12/3/2020 | JOHN JANSON |
| Permit Finaled | 12/3/2020 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/15/2020 | JOHN TRIANTAFYLLOS |
| Certificate of Compliance | Cleared | 6/15/2020 | PABLO ESTRADA |
| Sewer availability | Cleared | 6/15/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/23/2020 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 7/30/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Rough | 7/30/2020 | Approved | DAVID SCANTLIN |
| Underground Mechanical | 7/30/2020 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 8/4/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 8/4/2020 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2020 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 8/4/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 8/4/2020 | Approved | DAVID SCANTLIN |
| Underground Mechanical | 8/4/2020 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 8/6/2020 | Approved | DAVID SCANTLIN |
| Green Building Rough | 8/6/2020 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 8/6/2020 | Approved | DAVID SCANTLIN |
| Insulation | 8/6/2020 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 8/6/2020 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 8/12/2020 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 10/9/2020 | Approved | DAVID SCANTLIN |
| Final | 10/9/2020 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 10/9/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Final | 10/9/2020 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 10/9/2020 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 10/9/2020 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 10/9/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 10/9/2020 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 10/21/2020 | Approved | DAVID SCANTLIN |
| Final | 10/21/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 10/21/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Final | 10/21/2020 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 10/21/2020 | Approved | DAVID SCANTLIN |
| Service/Power Release | 10/21/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Final | 11/24/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Final | 11/24/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Green Building Final | 11/24/2020 | Approved | WILLIAM KUEHN |
| HVAC-Final | 11/24/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| PLUMBING-Final | 11/24/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Service/Power Release | 11/24/2020 | Not Required | WILLIAM KUEHN |
| ELECTRICAL-Final | 12/1/2020 | Approved | DAVID SCANTLIN |
| Final | 12/1/2020 | OK to Issue CofO | DAVID SCANTLIN |
| HVAC-Final | 12/1/2020 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 12/1/2020 | Approved | DAVID SCANTLIN |