9912 N TAMARACK AVE 91331
Certificate Information: 9912 N TAMARACK AVE 91331
- Application / Permit
- 20016-20000-12839
- Plan Check / Job No.
- B20VN07367
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 20' X 24' (E) REC. ROOM AND 5' X 20' PORTION OF (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT. CONVERT 15' X 18' REMAINING PORTION OF GARAGE TO STORAGE. ALL WORK PER WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 04/14/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 2/5/2021
- Issuing Office
- Current Status
- CofO Issued on 10/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2020 | RAPHAEL ROSAS |
| Corrections Issued | 8/1/2020 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 1/13/2021 | RAPHAEL ROSAS |
| Issued | 2/5/2021 | APPLICANT |
| CofO in Progress | 7/1/2021 | MARK BEVELAQUA |
| CofO in Progress | 7/1/2021 | JOSEPH BRENEK |
| CofO Issued | 10/20/2021 | DAVID JAMES |
| Permit Finaled | 10/20/2021 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 1/21/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 1/21/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/16/2021 | Approved | THOMAS WOODS |
| BUILDING-Rough-Frame | 5/5/2021 | Not Ready for Inspection | JOSEPH BRENEK |
| Green Building Rough | 5/5/2021 | Not Ready for Inspection | JOSEPH BRENEK |
| BUILDING-Rough-Frame | 5/7/2021 | Not Ready for Inspection | JOSEPH BRENEK |
| Green Building Rough | 5/7/2021 | Not Ready for Inspection | JOSEPH BRENEK |
| BUILDING-Rough-Frame | 5/18/2021 | Approved | JOSEPH BRENEK |
| ELECTRICAL-Rough | 5/18/2021 | Approved | JOSEPH BRENEK |
| Green Building Rough | 5/18/2021 | Approved | JOSEPH BRENEK |
| PLUMBING-Rough | 5/18/2021 | Corrections Issued | JOSEPH BRENEK |
| Gas Test | 5/24/2021 | Partial Inspection | JASON BRANNON |
| PLUMBING-Rough | 5/24/2021 | Approved | JASON BRANNON |
| Insulation | 5/28/2021 | Corrections Issued | KIM BEAUCHAMP |
| Drywall Nailing | 6/2/2021 | Not Ready for Inspection | JOSEPH BRENEK |
| Drywall Nailing | 6/7/2021 | Not Ready for Inspection | JOSEPH BRENEK |
| Drywall Nailing | 6/11/2021 | Approved | JOSEPH BRENEK |
| ELECTRICAL-Final | 6/28/2021 | Approved | JOSEPH BRENEK |
| Final | 6/28/2021 | OK to Issue CofO | JOSEPH BRENEK |
| Green Building Final | 6/28/2021 | Approved | JOSEPH BRENEK |
| SGSOV-Seismic Gas S/O Valve | 6/28/2021 | SGSOV Approved | JOSEPH BRENEK |
| Smoke Detectors | 6/28/2021 | Approved | JOSEPH BRENEK |