17522 W HAYNES ST 91406

Certificate Information: 17522 W HAYNES ST 91406

Application / Permit
20016-20000-12799
Plan Check / Job No.
B20VN07341
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-3" X 20'-2" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT. ALL WORK PER ENG
Permit Issued
Issued on 9/4/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/29/2020 APPLICANT
Assigned to Plan Check Engineer 6/4/2020 MARVEL DELACRUZ
Corrections Issued 6/9/2020 MARVEL DELACRUZ
Building Plans Picked Up 6/11/2020 APPLICANT
Applicant returned to address corrections 8/10/2020 RAPHAEL ROSAS
Plan Check Approved 8/26/2020 RAPHAEL ROSAS
Issued 9/4/2020 APPLICANT
CofO in Progress 2/18/2021 STEVEN BACK
CofO Issued 2/19/2021 DONALD SUNSERI
Permit Finaled 2/19/2021 DONALD SUNSERI

Permit Application Clearance Information

Address approval Cleared 6/17/2020 GABRIEL ROBLES
Sewer availability Cleared 6/17/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 6/22/2020 GABRIEL ROBLES
ZI Cleared 6/23/2020 STEVEN WECHSLER
Hydrant and Access approval Cleared 7/20/2020 KURT CORRAL

Contact Information

Contractor Better Together Builders Inc; Lic. No.: 1047689-B 23105 DELORASA STREET      WOODLAND HILLS, CA 91367
Engineer Standley,, Craig Erick; Lic. No.: C87675 6631 MURIETTA AVE      LOS ANGELES, CA 91405

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 10/1/2020 Approved STEVEN BACK
Underground Mechanical 10/1/2020 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 10/13/2020 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 10/13/2020 Approved STEVEN BACK
Pre-Inspection 10/22/2020 Approved STEVEN BACK
ELECTRICAL-Rough 11/6/2020 Corrections Issued STEVEN BACK
PLUMBING-Rough 11/6/2020 Approved STEVEN BACK
BUILDING-Rough-Frame 11/13/2020 Approved STEVEN BACK
ELECTRICAL-Rough 11/13/2020 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/13/2020 Approved STEVEN BACK
Green Building Rough 11/13/2020 Approved STEVEN BACK
HVAC-Rough 11/13/2020 Approved STEVEN BACK
Insulation 11/13/2020 Partial Approval STEVEN BACK
Interior/Exterior Lathing 11/13/2020 Partial Approval STEVEN BACK
Shower Pan 11/13/2020 Approved STEVEN BACK
Insulation 11/19/2020 Approved STEVEN BACK
Interior/Exterior Lathing 11/19/2020 Approved STEVEN BACK
Drywall Nailing 12/1/2020 Approved STEVEN BACK
Final 2/8/2021 Corrections Issued STEVEN BACK
Green Building Final 2/8/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 2/8/2021 SGSOV Not Ready STEVEN BACK
Smoke Detectors 2/8/2021 Not Ready for Inspection STEVEN BACK
Final 2/18/2021 OK to Issue CofO STEVEN BACK
SGSOV-Seismic Gas S/O Valve 2/18/2021 SGSOV Approved STEVEN BACK
Service/Power Release 2/18/2021 Approved STEVEN BACK
Smoke Detectors 2/18/2021 Approved STEVEN BACK