10506 N PLAINVIEW AVE 91042
Certificate Information: 10506 N PLAINVIEW AVE 91042
- Application / Permit
- 20016-20000-12748
- Plan Check / Job No.
- B20VN07313
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 32' X 28 IRREGULAR SHAPED STORAGE/ RECREATION BUILDING TO ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 6/29/2020
- Issuing Office
- Current Status
- CofO Issued on 10/21/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2020 | DAWN MC NULTY |
| Corrections Issued | 6/5/2020 | DAWN MC NULTY |
| Building Plans Picked Up | 6/9/2020 | APPLICANT |
| Plan Check Approved | 6/24/2020 | ROSENDO MEDINA |
| Issued | 6/29/2020 | APPLICANT |
| CofO in Progress | 9/9/2020 | MATTHEW NELSON |
| CofO Issued | 10/21/2020 | MICHAEL SMITH |
| Permit Finaled | 10/21/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/12/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 6/12/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/8/2020 | Approved | MATTHEW NELSON |
| Green Building Rough | 7/8/2020 | Approved | MATTHEW NELSON |
| Pre-Inspection | 7/16/2020 | Corrections Issued | MATTHEW NELSON |
| Special/Order Compliance | 7/16/2020 | Partial Inspection | PIERRE VEGA |
| Pre-Inspection | 7/29/2020 | Corrections Issued | MATTHEW NELSON |
| Special/Order Compliance | 7/29/2020 | Partial Approval | PIERRE VEGA |
| ELECTRICAL-Rough | 8/19/2020 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 8/25/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 8/25/2020 | Approved | MATTHEW NELSON |
| Drywall Nailing | 8/27/2020 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 8/27/2020 | Approved | MATTHEW NELSON |
| Final | 8/27/2020 | Partial Approval | MATTHEW NELSON |
| Green Building Final | 8/27/2020 | Approved | MATTHEW NELSON |
| HVAC-Final | 8/27/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 8/27/2020 | Approved | MATTHEW NELSON |
| Smoke Detectors | 8/27/2020 | Approved | MATTHEW NELSON |
| Final | 9/9/2020 | OK to Issue CofO | MATTHEW NELSON |