5124 N WINNETKA AVE 91364

Certificate Information: 5124 N WINNETKA AVE 91364

Application / Permit
20016-20000-12649
Plan Check / Job No.
B20VN07271
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR NON-STRUCTURAL REMODEL TO (E) SFD TO CONVERT (E) BATHROOM AND PORTION OF (E) BEDROOM TO NEW BEDROOM AND CONVERT (E) FAU CLOSET TO NEW BATHROOM. RE-ROOF AND REPLACE ALL WINDOWS (SAME SIZE AND LOCATION).
Permit Issued
Issued on 6/25/2020
Issuing Office
Current Status
Permit Finaled on 4/26/2021

Permit Application Status History

Submitted 5/28/2020 APPLICANT
Assigned to Plan Check Engineer 6/1/2020 ROSENDO MEDINA
Corrections Issued 6/2/2020 ROSENDO MEDINA
No Progress 6/3/2020 ROSENDO MEDINA
Plan Check Approved 6/3/2020 ROSENDO MEDINA
Issued 6/25/2020 APPLICANT
Permit Finaled 4/26/2021 DAVID SANDOVAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/25/2020 ADRIAN CASTRO
Sewer availability Cleared 6/25/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 7/21/2020 Approved DAVID SANDOVAL
ELECTRICAL-Rough 10/15/2020 Not Ready for Inspection PAUL CHOPP
HVAC-Rough 10/15/2020 Not Ready for Inspection PAUL CHOPP
Interior/Exterior Lathing 10/15/2020 Not Ready for Inspection PAUL CHOPP
PLUMBING-Rough 10/15/2020 Corrections Issued PAUL CHOPP
ELECTRICAL-Rough 10/19/2020 Not Ready for Inspection PAUL CHOPP
HVAC-Rough 10/19/2020 Not Ready for Inspection PAUL CHOPP
PLUMBING-Rough 10/19/2020 Not Ready for Inspection PAUL CHOPP
ELECTRICAL-Rough 11/5/2020 Corrections Issued JEFFREY PARD
Footing/Foundation/Slab 11/5/2020 Approved JEFFREY PARD
HVAC-Rough 11/5/2020 Approved JEFFREY PARD
PLUMBING-Rough 11/5/2020 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 11/12/2020 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 11/12/2020 Corrections Issued MICHAEL TEMPLE
ELECTRICAL-Rough 11/17/2020 Approved DONALD SUNSERI
PLUMBING-Rough 11/17/2020 Approved DONALD SUNSERI
Interior/Exterior Lathing 11/25/2020 Partial Approval DONALD SUNSERI
Wood Frame 11/25/2020 Partial Approval DONALD SUNSERI
BUILDING-Rough-Frame 11/30/2020 Approved VINCENT HANLEY
Green Building Rough 11/30/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 11/30/2020 Not Ready for Inspection VINCENT HANLEY
Wood Frame 11/30/2020 Approved VINCENT HANLEY
Insulation 12/3/2020 Not Ready for Inspection DONALD SUNSERI
Insulation 12/7/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 12/7/2020 Partial Approval VINCENT HANLEY
Drywall Nailing 12/10/2020 Approved VINCENT HANLEY
Shower Pan 12/14/2020 Approved DAVID SCANTLIN
ELECTRICAL-Final 4/22/2021 Approved DAVID SANDOVAL
Final 4/22/2021 Corrections Issued DAVID SANDOVAL
HVAC-Final 4/22/2021 Approved DAVID SANDOVAL
PLUMBING-Final 4/22/2021 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 4/22/2021 SGSOV Not Ready DAVID SANDOVAL
Smoke Detectors 4/22/2021 Approved DAVID SANDOVAL
Final 4/26/2021 Permit Finaled DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 4/26/2021 SGSOV Approved DAVID SANDOVAL