16652 W CHARMEL LANE 90272

Certificate Information: 16652 W CHARMEL LANE 90272

Application / Permit
20016-20000-12631
Plan Check / Job No.
B20VN07250
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, REMOVE 10'-8" X 10'-3" SUNROOM REMOVE (E) FIREPLACE, REMOVE AND REPLACE (E) 6'-9" X 9'-6" FRONT PORCH ALL WORK PER ENGINEERING
Permit Issued
Issued on 3/4/2021
Issuing Office
Current Status
CofO Issued on 4/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/27/2020 APPLICANT
Assigned to Plan Check Engineer 6/19/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 6/23/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 7/10/2020 OMID HEDAYAT
Building Plans Picked Up 7/10/2020 APPLICANT
Plan Check Approved 3/4/2021 SEWADA ZADOORAN MILAGARDI
Issued 3/4/2021 APPLICANT
CofO in Progress 4/4/2022 ANDREW NAVE
Permit Finaled 4/6/2022 DANIEL ORRANTE
CofO Issued 4/6/2022 DANIEL ORRANTE
Permit Finaled 4/6/2022 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/5/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 11/20/2020 DINAH GARIN
Coastal Zone Cleared 11/23/2020 DENZEL HENDERSON
Coastal Zone Cleared 11/23/2020 DENZEL HENDERSON
Coastal Zone Cleared 11/23/2020 DENZEL HENDERSON
Miscellaneous Cleared 11/23/2020 DENZEL HENDERSON
ZA Case Cleared 11/23/2020 DENZEL HENDERSON
ZI Cleared 11/23/2020 DENZEL HENDERSON
Grading Pre-Inspection Cleared 3/1/2021 PATRICK MISCHLICH

Contact Information

Contractor Van Burt L; Lic. No.: 383463-B P O BOX 828      FRAZIER PARK, CA 93225
Engineer Kessler,, Dale Edward; Lic. No.: C58524 16043 HART ST      VAN NUYS, CA 91406

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/21/2021 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 5/25/2021 Approved ANDREW NAVE
BUILDING-Rough-Frame 7/28/2021 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 7/28/2021 Partial Approval ANDREW NAVE
Green Building Rough 7/28/2021 Not Ready for Inspection ANDREW NAVE
Wood Frame 7/28/2021 Partial Approval ANDREW NAVE
ELECTRICAL-Rough 8/5/2021 Corrections Issued ANDREW NAVE
HVAC-Rough 8/5/2021 Not Ready for Inspection ANDREW NAVE
PLUMBING-Rough 8/5/2021 Approved ANDREW NAVE
ELECTRICAL-Rough 9/16/2021 Approved ANDREW NAVE
HVAC-Rough 9/16/2021 Corrections Issued ANDREW NAVE
BUILDING-Rough-Frame 9/21/2021 Approved ANDREW NAVE
Green Building Rough 9/21/2021 Approved ANDREW NAVE
Insulation 9/21/2021 Not Ready for Inspection ANDREW NAVE
Wood Frame 9/21/2021 Approved ANDREW NAVE
HVAC-Rough 9/24/2021 Approved ANDREW NAVE
Insulation 9/24/2021 Approved ANDREW NAVE
Drywall Nailing 11/12/2021 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 2/22/2022 Approved ANDREW NAVE
Drywall Nailing 3/2/2022 Approved ANDREW NAVE
ELECTRICAL-Final 3/25/2022 Corrections Issued ANDREW NAVE
Final 3/25/2022 Not Ready for Inspection ANDREW NAVE
Green Building Final 3/25/2022 Corrections Issued ANDREW NAVE
HVAC-Final 3/25/2022 Corrections Issued ANDREW NAVE
PLUMBING-Final 3/25/2022 Not Ready for Inspection ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 3/25/2022 SGSOV Approved ANDREW NAVE
Smoke Detectors 3/25/2022 Approved ANDREW NAVE
ELECTRICAL-Final 3/30/2022 Approved ANDREW NAVE
Final 3/30/2022 Not Ready for Inspection ANDREW NAVE
Green Building Final 3/30/2022 Approved ANDREW NAVE
PLUMBING-Final 4/1/2022 Corrections Issued JUAN VALENZUELA
Final 4/4/2022 OK to Issue CofO ANDREW NAVE
HVAC-Final 4/4/2022 Approved ANDREW NAVE
PLUMBING-Final 4/4/2022 Approved ANDREW NAVE