6247 N GOODLAND PL 91606
Certificate Information: 6247 N GOODLAND PL 91606
- Application / Permit
- 20016-20000-12627
- Plan Check / Job No.
- B20VN07244
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 14'6" X 10' STORAGE AND (E) 20' X 18'2" DETACHED GARAGE/ REC. ROOM TO ACCESSORY DWELLING UNIT PER GCS 65852.2 (e)(1)(A). WORK PER WFPP.
- Permit Issued
- Issued on 11/2/2020
- Issuing Office
- Current Status
- CofO Issued on 2/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2020 | RARES BODEA |
| Corrections Issued | 6/11/2020 | RARES BODEA |
| Building Plans Picked Up | 6/12/2020 | APPLICANT |
| Applicant returned to address corrections | 10/30/2020 | ROSENDO MEDINA |
| Plan Check Approved | 11/2/2020 | ROSENDO MEDINA |
| Issued | 11/2/2020 | APPLICANT |
| CofO in Progress | 2/15/2022 | CHRISTOPHE COCHRAN |
| CofO in Progress | 2/15/2022 | CHRISTOPHE COCHRAN |
| Permit Finaled | 2/17/2022 | MICHAEL SMITH |
| CofO Issued | 2/17/2022 | MICHAEL SMITH |
| Permit Finaled | 2/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/27/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 7/27/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2020 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 10/7/2020 | WALTER RAMIREZ |
| Construction within easement | Cleared | 10/7/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/11/2020 | Partial Inspection | BRENDAN LOONEY |
| Underground Mechanical | 12/30/2020 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 3/15/2021 | Not Ready for Inspection | DAVID MATSON |
| HVAC-Rough | 3/15/2021 | Not Ready for Inspection | DAVID MATSON |
| Underground Mechanical | 3/15/2021 | Partial Approval | DAVID MATSON |
| Wood Frame | 3/15/2021 | Corrections Issued | DAVID MATSON |
| Footing/Foundation/Slab | 6/1/2021 | Corrections Issued | RICHARD DOCKUS |
| Deputy Drilled-In Anchors | 6/9/2021 | No Result Entered | GREG ALLTON |
| Footing/Foundation/Slab | 6/14/2021 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 8/5/2021 | No Access for Inspection | DANIEL DREW |
| HVAC-Rough | 8/5/2021 | No Access for Inspection | DANIEL DREW |
| Sewer | 8/5/2021 | No Access for Inspection | DANIEL DREW |
| ELECTRICAL-Rough | 8/12/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| HVAC-Rough | 8/12/2021 | Approved | CHRISTOPHE COCHRAN |
| Sewer | 8/12/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 9/3/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 9/3/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 9/8/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 9/8/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 9/13/2021 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 9/13/2021 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 9/13/2021 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 9/13/2021 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 9/15/2021 | Approved | MATTHEW NELSON |
| Insulation | 9/15/2021 | Approved | MATTHEW NELSON |
| Final | 11/18/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Final | 11/18/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2021 | SGSOV Not Ready | CHRISTOPHE COCHRAN |
| Smoke Detectors | 11/18/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 11/24/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Final | 11/24/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 11/24/2021 | SGSOV Not Ready | CHRISTOPHE COCHRAN |
| Smoke Detectors | 11/24/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 1/25/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 1/25/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 1/25/2022 | SGSOV Not Ready | CHRISTOPHE COCHRAN |
| Smoke Detectors | 1/25/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 2/1/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 2/1/2022 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 2/1/2022 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 2/1/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 2/3/2022 | Conditional Approval | CHRISTOPHE COCHRAN |
| Final | 2/8/2022 | OK to Issue CofO | CHRISTOPHE COCHRAN |