3366 N SCADLOCK LANE 91403
Certificate Information: 3366 N SCADLOCK LANE 91403
- Application / Permit
- 20016-20000-12582
- Plan Check / Job No.
- B20VN07191
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) DWELLING TO RECONFIGURE FLOOR PLAN LAYOUT. RELOCATE AND REMODEL KITCHEN, AND ADD ONE NEW POWDER ROOM. COMPLY WITH DEPARTMENT ORDER effective date 05/22/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 9/15/2020
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 3/24/2021
Permit Application Status History
| Submitted | 5/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 6/17/2020 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 6/24/2020 | APPLICANT |
| Applicant returned to address corrections | 8/14/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 9/3/2020 | JEROME MAGAT PALMA |
| Issued | 9/15/2020 | APPLICANT |
| Permit Finaled | 3/24/2021 | GORDON ZUBER |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/24/2020 | BARTON HOLMES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/14/2020 | Not Ready for Inspection | GORDON ZUBER |
| Footing/Foundation/Slab | 10/14/2020 | Corrections Issued | GORDON ZUBER |
| MERV13>=Rough | 10/14/2020 | Not Ready for Inspection | GORDON ZUBER |
| Footing/Foundation/Slab | 10/15/2020 | Not Ready for Inspection | GORDON ZUBER |
| Wood Frame | 10/15/2020 | Corrections Issued | GORDON ZUBER |
| Deputy Drilled-In Anchors | 10/16/2020 | Conditional Approval | GABRIEL HERRERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2020 | Approved | GORDON ZUBER |
| Footing/Foundation/Slab | 10/22/2020 | Approved | GORDON ZUBER |
| BUILDING-Rough-Frame | 11/9/2020 | Not Ready for Inspection | GORDON ZUBER |
| MERV13>=Rough | 11/9/2020 | Not Ready for Inspection | GORDON ZUBER |
| ELECTRICAL-Rough | 11/10/2020 | Not Ready for Inspection | GORDON ZUBER |
| PLUMBING-Rough | 11/10/2020 | Not Ready for Inspection | GORDON ZUBER |
| HVAC-Rough | 11/12/2020 | Not Ready for Inspection | GORDON ZUBER |
| PLUMBING-Rough | 11/12/2020 | Not Ready for Inspection | GORDON ZUBER |
| HVAC-Rough | 11/18/2020 | Approved | JOHN TCHANG |
| PLUMBING-Rough | 11/18/2020 | Approved | JOHN TCHANG |
| Insulation | 11/23/2020 | Approved | GORDON ZUBER |
| Shower Pan | 11/23/2020 | Approved | GORDON ZUBER |
| Drywall Nailing | 12/1/2020 | Approved | GORDON ZUBER |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2020 | Corrections Issued | GORDON ZUBER |
| Interior/Exterior Lathing | 12/23/2020 | Approved | GORDON ZUBER |
| Grounding or Bonding | 1/4/2021 | Partial Approval | GORDON ZUBER |
| ELECTRICAL-Rough | 1/19/2021 | Not Ready for Inspection | GORDON ZUBER |
| PLUMBING-Rough | 1/19/2021 | Not Ready for Inspection | GORDON ZUBER |
| BUILDING-Rough-Frame | 3/24/2021 | Approved | GORDON ZUBER |
| Final | 3/24/2021 | Permit Finaled | GORDON ZUBER |
| MERV13>=Final | 3/24/2021 | Approved | GORDON ZUBER |
| MERV13>=Rough | 3/24/2021 | Approved | GORDON ZUBER |
| SGSOV-Seismic Gas S/O Valve | 3/24/2021 | SGSOV Approved | GORDON ZUBER |
| Smoke Detectors | 3/24/2021 | Approved | GORDON ZUBER |