Work Description
CONVERT (E) 20'-1" X 24'-4" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER WFPP
Permit Issued
Issued on 9/4/2020
Issuing Office
Current Status
CofO Issued on 5/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2020 APPLICANT
Assigned to Plan Check Engineer 5/27/2020 TROY DEGUZMAN
Corrections Issued 6/4/2020 TROY DEGUZMAN
Building Plans Picked Up 6/9/2020 APPLICANT
Plan Check Approved 8/26/2020 OMAR GARNICA
Issued 9/4/2020 APPLICANT
CofO in Progress 1/11/2021 THOMAS FINNILA
CofO Issued 5/25/2022 MICHAEL SMITH
Permit Finaled 5/25/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/11/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 6/11/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 6/11/2020 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 8/19/2020 RIDWAN HARDY
Construction within easement Cleared 8/19/2020 RIDWAN HARDY

Contact Information

Contractor M D M Custom Remodeling Inc; Lic. No.: 930166-B 5316 BABCOCK AVE      VALLEY VILLAGE, CA 91607
Engineer Azarbin,, Hamid Reza; Lic. No.: C64515 22655 COVELLO ST      WEST HILLS, CA 91307

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/17/2020 Approved THOMAS FINNILA
Underground Mechanical 9/17/2020 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 10/1/2020 Corrections Issued THOMAS FINNILA
Green Building Rough 10/1/2020 Approved THOMAS FINNILA
Rough-Elec/Plmb/HVAC 10/1/2020 Approved THOMAS FINNILA
BUILDING-Rough-Frame 10/19/2020 Approved THOMAS FINNILA
Insulation 10/19/2020 Approved THOMAS FINNILA
Rough-Elec/Plmb/HVAC 10/19/2020 Approved THOMAS FINNILA
Underground Mechanical 10/19/2020 Approved THOMAS FINNILA
Drywall Nailing 10/23/2020 Approved THOMAS FINNILA
Interior/Exterior Lathing 10/23/2020 Approved THOMAS FINNILA
Final 12/10/2020 Corrections Issued THOMAS FINNILA
Green Building Final 12/10/2020 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 12/10/2020 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 12/10/2020 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 12/30/2020 SGSOV Not Ready ARAM AVEDISIAN
Final 1/5/2021 Not Ready for Inspection THOMAS FINNILA
Green Building Final 1/5/2021 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 1/5/2021 SGSOV Approved THOMAS FINNILA
Smoke Detectors 1/5/2021 Corrections Issued THOMAS FINNILA
ELECTRICAL-Final 1/6/2021 Approved THOMAS FINNILA
HVAC-Final 1/6/2021 Approved THOMAS FINNILA
Final 1/11/2021 OK to Issue CofO THOMAS FINNILA
Green Building Final 1/11/2021 Approved THOMAS FINNILA
Smoke Detectors 1/11/2021 Approved THOMAS FINNILA