4227 N KLUMP AVE 91602
Certificate Information: 4227 N KLUMP AVE 91602
- Application / Permit
- 20016-20000-12514
- Plan Check / Job No.
- B20VN07168
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20'-1" X 24'-4" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER WFPP
- Permit Issued
- Issued on 9/4/2020
- Issuing Office
- Current Status
- CofO Issued on 5/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/27/2020 | TROY DEGUZMAN |
| Corrections Issued | 6/4/2020 | TROY DEGUZMAN |
| Building Plans Picked Up | 6/9/2020 | APPLICANT |
| Plan Check Approved | 8/26/2020 | OMAR GARNICA |
| Issued | 9/4/2020 | APPLICANT |
| CofO in Progress | 1/11/2021 | THOMAS FINNILA |
| CofO Issued | 5/25/2022 | MICHAEL SMITH |
| Permit Finaled | 5/25/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/11/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 6/11/2020 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 8/19/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/19/2020 | RIDWAN HARDY |
Contact Information
| Contractor | M D M Custom Remodeling Inc; Lic. No.: 930166-B | 5316 BABCOCK AVE VALLEY VILLAGE, CA 91607 |
| Engineer | Azarbin,, Hamid Reza; Lic. No.: C64515 | 22655 COVELLO ST WEST HILLS, CA 91307 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/17/2020 | Approved | THOMAS FINNILA |
| Underground Mechanical | 9/17/2020 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/1/2020 | Corrections Issued | THOMAS FINNILA |
| Green Building Rough | 10/1/2020 | Approved | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 10/1/2020 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/19/2020 | Approved | THOMAS FINNILA |
| Insulation | 10/19/2020 | Approved | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 10/19/2020 | Approved | THOMAS FINNILA |
| Underground Mechanical | 10/19/2020 | Approved | THOMAS FINNILA |
| Drywall Nailing | 10/23/2020 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 10/23/2020 | Approved | THOMAS FINNILA |
| Final | 12/10/2020 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 12/10/2020 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 12/10/2020 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 12/10/2020 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 12/30/2020 | SGSOV Not Ready | ARAM AVEDISIAN |
| Final | 1/5/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 1/5/2021 | Corrections Issued | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 1/5/2021 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 1/5/2021 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Final | 1/6/2021 | Approved | THOMAS FINNILA |
| HVAC-Final | 1/6/2021 | Approved | THOMAS FINNILA |
| Final | 1/11/2021 | OK to Issue CofO | THOMAS FINNILA |
| Green Building Final | 1/11/2021 | Approved | THOMAS FINNILA |
| Smoke Detectors | 1/11/2021 | Approved | THOMAS FINNILA |