719 N VISTA ST 90046

Certificate Information: 719 N VISTA ST 90046

Application / Permit
20016-20000-12461
Plan Check / Job No.
B20VN07124
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 17'-8" X 17'-10" GARAGE TO (N) ACCESSORY DWELLING UNIT AND ADD (N) 2ND STORY PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
Permit Issued
Issued on 1/4/2021
Issuing Office
Current Status
CofO Issued on 1/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2020 APPLICANT
Assigned to Plan Check Engineer 7/1/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 7/13/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 7/16/2020 OMID HEDAYAT
Building Plans Picked Up 7/17/2020 APPLICANT
Plan Check Approved 12/16/2020 SEWADA ZADOORAN MILAGARDI
Issued 1/4/2021 APPLICANT
CofO in Progress 11/19/2021 CHRIS CHRISTENSEN
Permit Finaled 1/22/2022 DEROLD HAUFF
CofO Issued 1/22/2022 DEROLD HAUFF
Permit Finaled 1/22/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/28/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 7/29/2020 ELAINE LEI
Sewer availability Cleared 7/29/2020 ELAINE LEI
Low Impact Development Cleared 10/21/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 10/22/2020 ELAINE LEI
Construction near power lines Cleared 11/20/2020 RIDWAN HARDY
Construction within easement Cleared 11/20/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 3/10/2021 Corrections Issued CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 3/10/2021 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 3/10/2021 Not Ready for Inspection CHRIS CHRISTENSEN
METHANE-Rough 3/10/2021 Approved CHRIS CHRISTENSEN
Wood Frame 3/19/2021 Partial Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 3/25/2021 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 4/13/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 4/26/2021 Corrections Issued CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/10/2021 Partial Approval CHRIS CHRISTENSEN
Sewer 5/21/2021 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/24/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 5/24/2021 Approved CHRIS CHRISTENSEN
Sewer 5/24/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/28/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 5/28/2021 Approved CHRIS CHRISTENSEN
HVAC-Rough 5/28/2021 Approved CHRIS CHRISTENSEN
Wood Frame 5/28/2021 Approved CHRIS CHRISTENSEN
Insulation 6/10/2021 Corrections Issued THOMAS LOGRASSO
Drywall Nailing 6/14/2021 Approved THOMAS LOGRASSO
Drywall Nailing 6/16/2021 Approved JESUS PINEDA
Gas Test 9/2/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 9/9/2021 Approved CHRIS CHRISTENSEN
HVAC-Final 10/15/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 10/15/2021 Approved CHRIS CHRISTENSEN
Service/Power Release 10/15/2021 Not Required CHRIS CHRISTENSEN
Final 10/22/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Footing/Foundation/Slab 10/22/2021 Approved CHRIS CHRISTENSEN
Green Building Final 10/22/2021 Approved CHRIS CHRISTENSEN
METHANE-Barrier 10/22/2021 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 10/22/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/22/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 10/22/2021 Approved CHRIS CHRISTENSEN
Final 11/2/2021 Corrections Issued CHRIS CHRISTENSEN
Final 11/18/2021 OK to Issue CofO CHRIS CHRISTENSEN