719 N VISTA ST 90046
Certificate Information: 719 N VISTA ST 90046
- Application / Permit
- 20016-20000-12461
- Plan Check / Job No.
- B20VN07124
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 17'-8" X 17'-10" GARAGE TO (N) ACCESSORY DWELLING UNIT AND ADD (N) 2ND STORY PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 1/4/2021
- Issuing Office
- Current Status
- CofO Issued on 1/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 7/13/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 7/16/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 7/17/2020 | APPLICANT |
| Plan Check Approved | 12/16/2020 | SEWADA ZADOORAN MILAGARDI |
| Issued | 1/4/2021 | APPLICANT |
| CofO in Progress | 11/19/2021 | CHRIS CHRISTENSEN |
| Permit Finaled | 1/22/2022 | DEROLD HAUFF |
| CofO Issued | 1/22/2022 | DEROLD HAUFF |
| Permit Finaled | 1/22/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/28/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2020 | ELAINE LEI |
| Sewer availability | Cleared | 7/29/2020 | ELAINE LEI |
| Low Impact Development | Cleared | 10/21/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 10/22/2020 | ELAINE LEI |
| Construction near power lines | Cleared | 11/20/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/20/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/10/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 3/10/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| METHANE-Rough | 3/10/2021 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 3/19/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 3/25/2021 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 4/13/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 4/26/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 5/10/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Sewer | 5/21/2021 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 5/24/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 5/24/2021 | Approved | CHRIS CHRISTENSEN |
| Sewer | 5/24/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 5/28/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 5/28/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 5/28/2021 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 5/28/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 6/10/2021 | Corrections Issued | THOMAS LOGRASSO |
| Drywall Nailing | 6/14/2021 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 6/16/2021 | Approved | JESUS PINEDA |
| Gas Test | 9/2/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 9/9/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 10/15/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 10/15/2021 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 10/15/2021 | Not Required | CHRIS CHRISTENSEN |
| Final | 10/22/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 10/22/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 10/22/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Barrier | 10/22/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 10/22/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 10/22/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 10/22/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 11/2/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 11/18/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |