216 1/2 N AVENUE 52 90042
Certificate Information: 216 1/2 N AVENUE 52 90042
- Application / Permit
- 20016-20000-12379
- Plan Check / Job No.
- B20VN07105
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED (18'-3"x 21'-0") GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2 (e)(1)(A). WORK PER ENGINEER.
- Permit Issued
- Issued on 4/8/2021
- Issuing Office
- Current Status
- CofO Issued on 3/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/19/2020 | TROY DEGUZMAN |
| Corrections Issued | 6/21/2020 | TROY DEGUZMAN |
| Quality Review Completed | 6/23/2020 | CHON CHIO KUO |
| Green Plans Picked Up | 6/24/2020 | APPLICANT |
| Applicant returned to address corrections | 10/27/2020 | TROY DEGUZMAN |
| Plan Check Approved | 3/3/2021 | PETER MOSESIAN |
| Issued | 4/8/2021 | APPLICANT |
| Building Plans Picked Up | 4/13/2021 | APPLICANT |
| CofO in Progress | 2/15/2023 | AMY COLIN |
| Permit Finaled | 3/15/2023 | DEROLD HAUFF |
| CofO Issued | 3/15/2023 | DEROLD HAUFF |
| Permit Finaled | 3/15/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2020 | RENZ SORIANO |
| Address approval | Cleared | 7/27/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 7/28/2020 | RENZ SORIANO |
| Grading Pre-Inspection | Cleared | 8/14/2020 | PATRICK MISCHLICH |
| Hydrant and Access approval | Cleared | 9/1/2020 | MATTHEW CRAIG |
| CPC | Cleared | 9/30/2020 | KATIE DEBIASE |
| HPOZ | Cleared | 9/30/2020 | KATIE DEBIASE |
| ZI | Cleared | 9/30/2020 | KATIE DEBIASE |
| Construction near power lines | Cleared | 12/4/2020 | RIDWAN HARDY |
| Green Code | Cleared | 1/20/2021 | TROY DEGUZMAN |
Contact Information
| Contractor | Nunez General Contractors Inc; Lic. No.: 912178-B | P O BOX 1079 SOUTH GATE, CA 90280 |
| Engineer | Baich,, Brendon Chad; Lic. No.: C83347 | 1898 WILDROSE AVE POMONA, CA 91767 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/10/2021 | Not Ready for Inspection | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 10/14/2022 | Corrections Issued | AMY COLIN |
| PLUMBING-Rough | 10/14/2022 | Partial Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2022 | Partial Approval | AMY COLIN |
| Rough-Elec/Plmb/HVAC | 11/10/2022 | Not Ready for Inspection | AMY COLIN |
| BUILDING-Rough-Frame | 11/16/2022 | Corrections Issued | AMY COLIN |
| ELECTRICAL-Rough | 11/16/2022 | Approved | AMY COLIN |
| HVAC-Rough | 11/16/2022 | Approved | AMY COLIN |
| PLUMBING-Rough | 11/16/2022 | Corrections Issued | AMY COLIN |
| Insulation | 11/29/2022 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 11/29/2022 | Partial Approval | AMY COLIN |
| BUILDING-Rough-Frame | 12/9/2022 | Approved | AMY COLIN |
| PLUMBING-Rough | 12/9/2022 | Approved | AMY COLIN |
| Shower Pan | 12/9/2022 | Approved | AMY COLIN |
| Drywall Nailing | 12/12/2022 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 12/12/2022 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 1/20/2023 | Corrections Issued | AMY COLIN |
| Final | 1/20/2023 | Corrections Issued | AMY COLIN |
| HVAC-Final | 1/20/2023 | Approved | AMY COLIN |
| PLUMBING-Final | 1/20/2023 | Approved | AMY COLIN |
| ELECTRICAL-Final | 1/26/2023 | Approved | AMY COLIN |
| Final | 1/26/2023 | Partial Inspection | AMY COLIN |
| HVAC-Final | 1/26/2023 | Approved | AMY COLIN |
| PLUMBING-Final | 1/26/2023 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 1/26/2023 | SGSOV Approved | AMY COLIN |
| Service/Power Release | 1/26/2023 | Approved | AMY COLIN |
| Smoke Detectors | 1/26/2023 | Approved | AMY COLIN |
| Final | 2/15/2023 | OK to Issue CofO | AMY COLIN |