6740-6744 1/2 W COLGATE AVE 90048
Certificate Information: 6740-6744 1/2 W COLGATE AVE 90048
- Application / Permit
- 20016-20000-12021
- Plan Check / Job No.
- B20VN06924
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT 25'-9" X 20'-2" IRREG SHAPED ATTACHED GARAGE INTO ACCESSORY DWELLING UNIT (336 SQ FT) PER GCS 65852.2(e)(1)(C). SEE COMMENTS.
- Permit Issued
- Issued on 4/2/2022
- Issuing Office
- Current Status
- CofO Issued on 5/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 6/16/2020 | JEROME MAGAT PALMA |
| Quality Review Completed | 6/19/2020 | STEVEN KIM |
| Green Plans Picked Up | 6/26/2020 | APPLICANT |
| Applicant returned to address corrections | 9/21/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 1/26/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 1/27/2022 | APPLICANT |
| Issued | 4/2/2022 | APPLICANT |
| CofO in Progress | 5/18/2023 | JEREMY TODD |
| Permit Finaled | 5/31/2023 | DANIEL ORRANTE |
| CofO Issued | 5/31/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/31/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| CPC | Cleared | 9/23/2020 | LAUREN PADICK |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 10/21/2020 | CECILIO NAVARRO |
| Address approval | Cleared | 4/1/2021 | CECILIO NAVARRO |
| Public Works-Sewers | Cleared | 9/24/2021 | CECILIO NAVARRO |
| Construction near power lines | Cleared | 1/14/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/16/2022 | Conditional Approval | JEREMY TODD |
| Footing/Foundation/Slab | 12/16/2022 | Approved | JEREMY TODD |
| Pre-Inspection | 12/16/2022 | Corrections Issued | JEREMY TODD |
| ELECTRICAL-Rough | 1/24/2023 | Corrections Issued | JEREMY TODD |
| PLUMBING-Rough | 1/24/2023 | Approved | JEREMY TODD |
| Wood Frame | 1/24/2023 | Corrections Issued | JEREMY TODD |
| Deputy Drilled-In Anchors | 1/25/2023 | Conditional Approval | MICHAEL PELHAM |
| Insulation | 1/30/2023 | Partial Approval | JEREMY TODD |
| Wood Frame | 1/30/2023 | Conditional Approval | JEREMY TODD |
| ELECTRICAL-Rough | 2/3/2023 | Approved | JEREMY TODD |
| HVAC-Rough | 2/3/2023 | Not Ready for Inspection | JEREMY TODD |
| Insulation | 2/3/2023 | Conditional Approval | JEREMY TODD |
| Wood Frame | 2/3/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 2/16/2023 | Conditional Approval | CLAYTON GRAHAM |
| HVAC-Rough | 2/16/2023 | Corrections Issued | CLAYTON GRAHAM |
| Shower Pan | 2/16/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Rough | 2/24/2023 | Approved | JEREMY TODD |
| Shower Pan | 2/24/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 3/6/2023 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 5/10/2023 | Approved | JEREMY TODD |
| Final | 5/10/2023 | Corrections Issued | JEREMY TODD |
| Green Building Final | 5/10/2023 | Approved | JEREMY TODD |
| Green Building Rough | 5/10/2023 | Approved | JEREMY TODD |
| METHANE-Final | 5/10/2023 | Approved | JEREMY TODD |
| METHANE-Rough | 5/10/2023 | Approved | JEREMY TODD |
| SGSOV-Seismic Gas S/O Valve | 5/10/2023 | SGSOV Approved | JEREMY TODD |
| Smoke Detectors | 5/10/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Final | 5/17/2023 | Approved | JEREMY TODD |
| Final | 5/17/2023 | OK to Issue CofO | JEREMY TODD |
| HVAC-Final | 5/17/2023 | Approved | JEREMY TODD |
| PLUMBING-Final | 5/17/2023 | Approved | JEREMY TODD |