7503 N YARMOUTH AVE 91335

Certificate Information: 7503 N YARMOUTH AVE 91335

Application / Permit
20016-20000-11897
Plan Check / Job No.
B20VN06860
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE AND STORAGE ROOM TO NEW ACCESSORY DWELLING UNIT (930 SQ FT)
Permit Issued
Issued on 8/6/2020
Issuing Office
Current Status
CofO Issued on 10/13/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2020 APPLICANT
Assigned to Plan Check Engineer 5/27/2020 SELLA BENYAMIN
Corrections Issued 6/2/2020 SELLA BENYAMIN
Plan Check Approved 8/3/2020 JEROME MAGAT PALMA
Issued 8/6/2020 APPLICANT
CofO in Progress 9/23/2020 VINCENT HANLEY
CofO Issued 10/13/2020 DONALD SUNSERI
Permit Finaled 10/13/2020 DONALD SUNSERI

Permit Application Clearance Information

Address approval Cleared 7/21/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 7/21/2020 GABRIEL ROBLES
Sewer availability Cleared 7/21/2020 GABRIEL ROBLES
Construction near power lines Cleared 8/3/2020 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/13/2020 Approved VINCENT HANLEY
ELECTRICAL-Rough 8/17/2020 Approved VINCENT HANLEY
PLUMBING-Rough 8/17/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 8/19/2020 Approved VINCENT HANLEY
Green Building Rough 8/19/2020 Approved VINCENT HANLEY
HVAC-Rough 8/19/2020 Approved VINCENT HANLEY
Drywall Nailing 8/26/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/26/2020 Approved VINCENT HANLEY
ELECTRICAL-Final 9/8/2020 Corrections Issued VINCENT HANLEY
Final 9/8/2020 Corrections Issued VINCENT HANLEY
Green Building Final 9/8/2020 Approved VINCENT HANLEY
HVAC-Final 9/8/2020 Corrections Issued VINCENT HANLEY
PLUMBING-Final 9/8/2020 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/8/2020 SGSOV Approved VINCENT HANLEY
Smoke Detectors 9/8/2020 Approved VINCENT HANLEY
ELECTRICAL-Final 9/22/2020 Approved VINCENT HANLEY
Final 9/22/2020 OK to Issue CofO VINCENT HANLEY
HVAC-Final 9/22/2020 Approved VINCENT HANLEY
PLUMBING-Final 9/22/2020 Approved VINCENT HANLEY