3214-3214 1/2 E ARVIA ST 90065
Certificate Information: 3214-3214 1/2 E ARVIA ST 90065
- Application / Permit
- 20016-20000-11685
- Plan Check / Job No.
- B20VN06750
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 26' 4" X 15' 9" PORTION OF ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 5/22/2021
- Issuing Office
- Current Status
- CofO Issued on 12/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 6/21/2020 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 2/28/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 5/22/2021 | GURUNATH NESARAJAH |
| Issued | 5/22/2021 | APPLICANT |
| Building Plans Picked Up | 5/24/2021 | APPLICANT |
| CofO in Progress | 11/30/2021 | OSVALDO PARAMO |
| CofO in Progress | 11/30/2021 | OSVALDO PARAMO |
| Permit Finaled | 12/4/2021 | DEROLD HAUFF |
| CofO Issued | 12/4/2021 | DEROLD HAUFF |
| Permit Finaled | 12/4/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Supp. Use District POD/CDO/TDO | Cleared | 7/29/2020 | LAUREN PADICK |
| Address approval | Cleared | 8/12/2020 | CELINA MORENO |
| Sewer availability | Cleared | 8/12/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2020 | CELINA MORENO |
| Address approval | Cleared | 3/2/2021 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 4/27/2021 | PATRICK MISCHLICH |
| Construction near power lines | Cleared | 5/7/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/4/2021 | Corrections Issued | OSVALDO PARAMO |
| Pre-Inspection | 7/9/2021 | Corrections Issued | OSVALDO PARAMO |
| Pre-Inspection | 8/16/2021 | Not Ready for Inspection | WILLIAM WREN |
| Rough-Elec/Plmb/HVAC | 8/23/2021 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Final | 9/16/2021 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Final | 9/16/2021 | Approved | WILLIAM WREN |
| ELECTRICAL-Final | 9/21/2021 | Approved | OSVALDO PARAMO |
| Wood Frame | 9/21/2021 | Approved | OSVALDO PARAMO |
| Deputy Wood Construction | 9/28/2021 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2021 | Approved | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 9/29/2021 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 10/7/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 10/14/2021 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 10/26/2021 | Approved | OSVALDO PARAMO |
| Final | 10/26/2021 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 10/26/2021 | Approved | OSVALDO PARAMO |
| Green Building Rough | 10/26/2021 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 10/26/2021 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 10/26/2021 | Approved | OSVALDO PARAMO |
| Final | 11/12/2021 | Corrections Issued | OSVALDO PARAMO |
| Final | 11/29/2021 | OK to Issue CofO | OSVALDO PARAMO |