18351 W FRIAR ST 91335

Certificate Information: 18351 W FRIAR ST 91335

Application / Permit
20016-20000-11674
Plan Check / Job No.
B20VN06743
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 21'-0" X 18'-0" DETACHED GARAGE INTO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 8/5/2020
Issuing Office
Current Status
CofO Issued on 1/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2020 APPLICANT
Assigned to Plan Check Engineer 5/20/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 5/29/2020 SEWADA ZADOORIAN MILAGARDI
Building Plans Picked Up 6/1/2020 APPLICANT
Applicant returned to address corrections 6/19/2020 HAYATO TSUCHIYA
Plan Check Approved 7/16/2020 JEROME MAGAT PALMA
Issued 8/5/2020 APPLICANT
CofO in Progress 1/15/2021 DAVID SCANTLIN
Permit Finaled 1/22/2021 JOHN JANSON
CofO Issued 1/22/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/2/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 6/2/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 6/2/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 6/11/2020 JOHN TRIANTAFYLLOS
Miscellaneous Cleared 6/16/2020 MIGUEL GAMBOA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/6/2020 Corrections Issued STEVEN BACK
Pre-Inspection 8/6/2020 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 8/19/2020 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 8/19/2020 Corrections Issued STEVEN BACK
SGSOV-Seismic Gas S/O Valve 8/19/2020 SGSOV Not Ready STEVEN BACK
Footing/Foundation/Slab 8/21/2020 Approved STEVEN BACK
Pre-Inspection 8/21/2020 Partial Approval STEVEN BACK
Deputy Wood Construction 9/3/2020 No Access for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/16/2020 Corrections Issued STEVEN BACK
Green Building Rough 9/16/2020 Not Ready for Inspection STEVEN BACK
Deputy Wood Construction 9/24/2020 No Access for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/25/2020 Approved STEVEN BACK
Green Building Rough 9/25/2020 Not Ready for Inspection STEVEN BACK
Wood Frame 9/25/2020 Partial Approval STEVEN BACK
Green Building Rough 9/29/2020 Approved STEVEN BACK
Interior/Exterior Lathing 9/29/2020 Partial Approval STEVEN BACK
Wood Frame 9/29/2020 Approved STEVEN BACK
Insulation 10/1/2020 Approved STEVEN BACK
Drywall Nailing 10/16/2020 Approved STEVEN BACK
Interior/Exterior Lathing 10/16/2020 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 10/23/2020 Approved STEVEN BACK
Final 12/24/2020 Corrections Issued STEVEN BACK
Green Building Final 12/24/2020 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 12/24/2020 SGSOV Not Ready STEVEN BACK
Smoke Detectors 12/24/2020 Approved STEVEN BACK
Insulation 12/30/2020 Partial Inspection PAUL CHOPP
Final 1/6/2021 Corrections Issued BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 1/6/2021 SGSOV Approved BRENDAN LOONEY
Final 1/14/2021 OK to Issue CofO DAVID SCANTLIN