934 S LAKE ST UNIT 1-5 90006
Certificate Information: 934 S LAKE ST UNIT 1-5 90006
- Application / Permit
- 20016-20000-11651
- Plan Check / Job No.
- B20VN06732
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT (E) 16'4" X 39'7" PORTION OF (E) APARTMENT UNIT TO ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 8/21/2020
- Issuing Office
- Current Status
- CofO Issued on 11/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2020 | RARES BODEA |
| Corrections Issued | 6/22/2020 | RARES BODEA |
| Quality Review Completed | 6/23/2020 | STEVEN KIM |
| Building Plans Picked Up | 6/24/2020 | APPLICANT |
| Applicant returned to address corrections | 7/15/2020 | RARES BODEA |
| Applicant returned to address corrections | 7/28/2020 | RARES BODEA |
| Plan Check Approved | 8/21/2020 | RARES BODEA |
| Issued | 8/21/2020 | APPLICANT |
| CofO in Progress | 11/17/2021 | TIMOTHY BUXTON |
| CofO Issued | 11/17/2021 | TED RIES |
| Permit Finaled | 11/17/2021 | TED RIES |
Permit Application Clearance Information
| Address approval | Cleared | 7/23/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 7/26/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2020 | CECILIO NAVARRO |
| Tenant Habitability Plan | Cleared | 8/11/2020 | MICHAEL SOTO |
| Redevelopment Project Area | Cleared | 8/20/2020 | GRACIELA ACOSTA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 12/22/2020 | Not Ready for Inspection | KATY RAMIREZ |
| Wood Frame | 12/22/2020 | Partial Inspection | KATY RAMIREZ |
| Wood Frame | 12/29/2020 | Approved | EDWIN GREGORYONA |
| Drywall Nailing | 1/6/2021 | Approved | DANIEL COLLINS |
| Final | 11/16/2021 | OK to Issue CofO | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 11/16/2021 | SGSOV Approved | TIMOTHY BUXTON |
| Smoke Detectors | 11/16/2021 | Approved | TIMOTHY BUXTON |