802 W 103RD ST 90044

Certificate Information: 802 W 103RD ST 90044

Application / Permit
20016-20000-11508
Plan Check / Job No.
B20VN06654
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-4" X 18' DETACHED GARAGE TO ACCESSORY DWELLING UNIT (330 SQ FT)
Permit Issued
Issued on 12/15/2020
Issuing Office
Current Status
CofO Issued on 5/31/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/15/2020 APPLICANT
Assigned to Plan Check Engineer 5/20/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 5/29/2020 SEWADA ZADOORIAN MILAGARDI
Building Plans Picked Up 6/1/2020 APPLICANT
Applicant returned to address corrections 7/28/2020 JEROME MAGAT PALMA
Applicant returned to address corrections 9/24/2020 JEROME MAGAT PALMA
Plan Check Approved 12/1/2020 JEROME MAGAT PALMA
Issued 12/15/2020 APPLICANT
CofO in Progress 5/20/2022 ALIZAH MAYAGOITIA
Permit Finaled 5/31/2022 DEROLD HAUFF
CofO Issued 5/31/2022 DEROLD HAUFF
Permit Finaled 5/31/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/23/2020 JUAN ASHTON
Sewer availability Cleared 6/23/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 6/24/2020 JUAN ASHTON
Construction near power lines Cleared 11/13/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/16/2021 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 4/8/2021 Corrections Issued EUGENE CASSIDY
Insulation 4/8/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 4/8/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 4/16/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 4/22/2021 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 4/29/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 5/6/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 5/18/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 5/20/2021 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 5/28/2021 Approved EUGENE CASSIDY
Footing/Foundation/Slab 6/10/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 6/16/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 6/18/2021 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 6/23/2021 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 6/29/2021 Approved ANSON MAGLASANG
Pre-Inspection 7/26/2021 Corrections Issued EUGENE CASSIDY
Pre-Inspection 11/8/2021 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 12/3/2021 Corrections Issued JOHN KLARIN
Green Building Rough 12/3/2021 Corrections Issued JOHN KLARIN
BUILDING-Rough-Frame 12/14/2021 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 12/14/2021 Corrections Issued EUGENE CASSIDY
Insulation 12/14/2021 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 12/14/2021 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 12/20/2021 Approved JOHN KLARIN
ELECTRICAL-Rough 12/20/2021 Approved JOHN KLARIN
Green Building Rough 12/20/2021 Approved JOHN KLARIN
Interior/Exterior Lathing 12/20/2021 Corrections Issued JOHN KLARIN
PLUMBING-Rough 12/20/2021 Approved JOHN KLARIN
Interior/Exterior Lathing 1/11/2022 Approved EUGENE CASSIDY
Shower Pan 1/11/2022 Approved EUGENE CASSIDY
Interior/Exterior Lathing 1/18/2022 Approved EUGENE CASSIDY
Drywall Nailing 2/9/2022 Approved JOHN KLARIN
Final 5/10/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 5/10/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 5/10/2022 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 5/10/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 5/19/2022 Approved ALIZAH MAYAGOITIA
Final 5/19/2022 Conditional Approval ALIZAH MAYAGOITIA
Green Building Final 5/19/2022 Approved ALIZAH MAYAGOITIA
HVAC-Final 5/19/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 5/19/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 5/19/2022 SGSOV Approved ALIZAH MAYAGOITIA
Final 5/20/2022 OK to Issue CofO ALIZAH MAYAGOITIA