10215 N LAUREL CANYON BLVD 91331

Certificate Information: 10215 N LAUREL CANYON BLVD 91331

Application / Permit
20016-20000-11271
Plan Check / Job No.
B20VN06528
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 22' X 22' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 6585.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) & (g). REMOVE 22' X 1' PORTION. WORK PER WFPP.
Permit Issued
Issued on 11/17/2020
Issuing Office
Current Status
CofO Issued on 3/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/12/2020 APPLICANT
Assigned to Plan Check Engineer 6/15/2020 ROSENDO MEDINA
Corrections Issued 6/15/2020 ROSENDO MEDINA
Issued 11/17/2020 APPLICANT
CofO in Progress 3/19/2024 ROBERT GOLD
Permit Finaled 3/22/2024 RUBEN SALAS
CofO Issued 3/22/2024 RUBEN SALAS
Permit Finaled 3/22/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/1/2020 GABRIEL ROBLES
Sewer availability Cleared 7/1/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/26/2020 GABRIEL ROBLES
Hydrant and Access approval Cleared 10/20/2020 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/10/2021 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 11/10/2021 Approved JESUS RODRIGUEZ
PLUMBING-Rough 11/10/2021 Partial Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 11/7/2023 Approved MICHEL ABAJAN
ELECTRICAL-Rough 11/7/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 11/7/2023 Partial Approval MICHEL ABAJAN
Gas Test 11/7/2023 Approved MICHEL ABAJAN
Green Building Rough 11/7/2023 Approved MICHEL ABAJAN
HVAC-Final 11/7/2023 Not Ready for Inspection MICHEL ABAJAN
MERV13>=Rough 11/7/2023 Approved MICHEL ABAJAN
METHANE-Rough 11/7/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 11/7/2023 Approved MICHEL ABAJAN
Insulation 11/16/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 11/16/2023 Approved MICHEL ABAJAN
Sewer 11/16/2023 Approved MICHEL ABAJAN
Drywall Nailing 2/7/2024 Approved MICHEL ABAJAN
Gas Test 2/20/2024 Approved MICHEL ABAJAN
Underground Mechanical 2/20/2024 Partial Approval MICHEL ABAJAN
Underground Mechanical 2/22/2024 Partial Approval MICHEL ABAJAN
ELECTRICAL-Final 3/1/2024 Not Ready for Inspection MICHEL ABAJAN
Final 3/1/2024 Corrections Issued MICHEL ABAJAN
Green Building Final 3/1/2024 Approved MICHEL ABAJAN
HVAC-Final 3/1/2024 Not Ready for Inspection MICHEL ABAJAN
MERV13>=Final 3/1/2024 Approved MICHEL ABAJAN
PLUMBING-Final 3/1/2024 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/1/2024 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 3/1/2024 Not Ready for Inspection MICHEL ABAJAN
Final 3/11/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/11/2024 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 3/11/2024 Approved JENNIFER RABUCHIN
Final 3/15/2024 Partial Inspection ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 3/15/2024 SGSOV Not Ready ROBERT GOLD
Final 3/18/2024 OK to Issue CofO ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 3/18/2024 SGSOV Approved ROBERT GOLD