1164-1166 S BEVERWIL DR 90035
Certificate Information: 1164-1166 S BEVERWIL DR 90035
- Application / Permit
- 20016-20000-11261
- Plan Check / Job No.
- B20VN06519
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EX ATT GARAGE INTO ACCESSORY DWELLING UNIT W/O ADDITION. ALL WORK PER WFPP. SEE COMMENTS
- Permit Issued
- Issued on 10/21/2021
- Issuing Office
- Current Status
- CofO Issued on 6/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 5/15/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 9/2/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 11/25/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 3/4/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 4/20/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 4/23/2021 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 7/30/2021 | APPLICANT |
| Issued | 10/21/2021 | APPLICANT |
| CofO in Progress | 6/14/2022 | KEVIN SARGSYAN |
| Permit Finaled | 6/28/2022 | DANIEL ORRANTE |
| CofO Issued | 6/28/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/28/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2020 | DINAH GARIN |
| Sewer availability | Cleared | 6/10/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2020 | DINAH GARIN |
Contact Information
| Contractor | Azlan; Lic. No.: 1015022-B | 9956 POULSEN AVENUE MONTCLAIR, CA 91763 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/16/2021 | Approved | KRISTEN CAUSEY |
| Deputy Drilled-In Anchors | 1/13/2022 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 2/4/2022 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 2/9/2022 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 2/9/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 3/16/2022 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2022 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 3/16/2022 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 3/22/2022 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 3/22/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2022 | Conditional Approval | EVAN COOPER |
| Green Building Rough | 3/22/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 3/22/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 3/22/2022 | Approved | EVAN COOPER |
| Deputy Drilled-In Anchors | 3/29/2022 | Approved | KEVIN SARGSYAN |
| Insulation | 3/29/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 3/29/2022 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 3/31/2022 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2022 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 3/31/2022 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 4/7/2022 | Approved | KEVIN SARGSYAN |
| Shower Pan | 4/7/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 4/14/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 5/24/2022 | Corrections Issued | BRENDAN LOONEY |
| Final | 5/24/2022 | Corrections Issued | BRENDAN LOONEY |
| Green Building Final | 5/24/2022 | Approved | BRENDAN LOONEY |
| HVAC-Final | 5/24/2022 | Conditional Approval | BRENDAN LOONEY |
| PLUMBING-Final | 5/24/2022 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 5/24/2022 | SGSOV Not Ready | BRENDAN LOONEY |
| Smoke Detectors | 5/24/2022 | Approved | BRENDAN LOONEY |
| Final | 6/2/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 6/2/2022 | SGSOV Not Ready | KEVIN SARGSYAN |
| Final | 6/8/2022 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 6/8/2022 | SGSOV Approved | EVAN COOPER |
| Final | 6/13/2022 | OK to Issue CofO | KEVIN SARGSYAN |