11825-11827 N KILLIMORE AVE 91326
Certificate Information: 11825-11827 N KILLIMORE AVE 91326
- Application / Permit
- 20016-20000-11259
- Plan Check / Job No.
- B20VN06518
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 23'-11" X 30'-0" ATTACHED 3-CAR GARAGE TO (N) ACCESSORY DWELLING UNIT PER WFPP
- Permit Issued
- Issued on 7/16/2020
- Issuing Office
- Current Status
- CofO Issued on 12/15/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2020 | DAWN MC NULTY |
| Corrections Issued | 5/27/2020 | DAWN MC NULTY |
| Building Plans Picked Up | 6/3/2020 | APPLICANT |
| Plan Check Approved | 7/15/2020 | JENNIFER LEE |
| Issued | 7/16/2020 | APPLICANT |
| CofO in Progress | 12/15/2020 | DAVID SCANTLIN |
| Permit Finaled | 12/15/2020 | JOHN JANSON |
| CofO Issued | 12/15/2020 | JOHN JANSON |
| Permit Finaled | 12/15/2020 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/9/2020 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 6/9/2020 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 6/9/2020 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 6/9/2020 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 6/9/2020 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 6/9/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/9/2020 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 7/6/2020 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/30/2020 | Approved | DAVID SCANTLIN |
| Underground Mechanical | 8/14/2020 | Approved | DAVID SCANTLIN |
| Deputy Drilled-In Anchors | 9/4/2020 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2020 | Partial Approval | DAVID SCANTLIN |
| Green Building Rough | 9/9/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 9/30/2020 | Approved | DAVID SCANTLIN |
| Green Building Rough | 9/30/2020 | Approved | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 9/30/2020 | Approved | DAVID SCANTLIN |
| Insulation | 10/13/2020 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 10/29/2020 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2020 | Approved | DAVID SCANTLIN |
| Gas Test | 11/5/2020 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 11/5/2020 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 12/14/2020 | Approved | DAVID SCANTLIN |
| Final | 12/14/2020 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 12/14/2020 | Approved | DAVID SCANTLIN |
| HVAC-Final | 12/14/2020 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 12/14/2020 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 12/14/2020 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 12/14/2020 | Approved | DAVID SCANTLIN |