12040 W STRATHERN ST 1-50 91605
Certificate Information: 12040 W STRATHERN ST 1-50 91605
- Application / Permit
- 20016-20000-11232
- Plan Check / Job No.
- B20VN06489
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT THE (E) 18'7" X 22'3" ATTACHED RECREATION ROOM INTO A (N) ACCESSORY DWELLING UNIT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/2/2020
- Issuing Office
- Current Status
- CofO Corrected on 3/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2020 | RARES BODEA |
| Corrections Issued | 5/20/2020 | RARES BODEA |
| Building Plans Picked Up | 5/22/2020 | APPLICANT |
| Plan Check Approved | 6/10/2020 | ALDO UBAU |
| Issued | 11/2/2020 | APPLICANT |
| CofO in Progress | 10/27/2021 | ANDREW DORSO |
| CofO Issued-Status Void | 10/27/2021 | JEFFREY DURAN |
| Permit Finaled-Status Void | 10/27/2021 | JEFFREY DURAN |
| Re-Activate Permit | 3/3/2025 | RICKEY JACKSON |
| Permit Finaled | 3/3/2025 | RICKEY JACKSON |
| CofO Corrected | 3/3/2025 | RICKEY JACKSON |
| Permit Finaled | 3/3/2025 | RICKEY JACKSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/27/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 5/27/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 5/27/2020 | JOHN TRIANTAFYLLOS |
| ZA Case | Cleared | 5/29/2020 | MIGUEL GAMBOA |
| ZI | Cleared | 5/29/2020 | MIGUEL GAMBOA |
| Tenant Habitability Plan | Cleared | 6/1/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Blondy Development Co Inc; Lic. No.: 487028-B | 16456 ROYAL HILLS DRIVE ENCINO, CA 91436 |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 21201 KITTRIDGE ST APT 9105 WOODLAND HILLS, CA 91303 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 11/10/2020 | Corrections Issued | ANDREW DORSO |
| Green Building Final | 11/10/2020 | Not Ready for Inspection | ANDREW DORSO |
| Green Building Rough | 11/10/2020 | Not Ready for Inspection | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 11/10/2020 | SGSOV Not Ready | ANDREW DORSO |
| Smoke Detectors | 11/10/2020 | Not Ready for Inspection | ANDREW DORSO |
| Wood Frame | 11/10/2020 | Not Ready for Inspection | ANDREW DORSO |
| Final | 5/26/2021 | Not Ready for Inspection | ANDREW DORSO |
| Green Building Final | 5/26/2021 | Approved | ANDREW DORSO |
| Green Building Rough | 5/26/2021 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 5/26/2021 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 5/26/2021 | Not Ready for Inspection | ANDREW DORSO |
| Wood Frame | 5/26/2021 | Approved | ANDREW DORSO |
| Final | 6/8/2021 | OK to Issue CofO | ANDREW DORSO |
| Smoke Detectors | 6/8/2021 | Approved | ANDREW DORSO |