6931-6933 N WILBUR AVE 91335

Certificate Information: 6931-6933 N WILBUR AVE 91335

Application / Permit
20016-20000-11052
Plan Check / Job No.
B20VN06405
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER WFPP
Permit Issued
Issued on 3/18/2021
Issuing Office
Current Status
CofO Issued on 2/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2020 APPLICANT
Assigned to Plan Check Engineer 5/13/2020 NILOOFAR MEHRAIN
Corrections Issued 5/21/2020 NILOOFAR MEHRAIN
Building Plans Picked Up 5/22/2020 APPLICANT
Plan Check Approved 10/5/2020 MANUEL GARCIA
Issued 3/18/2021 APPLICANT
CofO in Progress 7/12/2022 JEFFREY BULL
Permit Finaled 2/25/2023 DANIEL ORRANTE
CofO Issued 2/25/2023 DANIEL ORRANTE
Permit Finaled 2/25/2023 DANIEL ORRANTE

Permit Application Clearance Information

ZI Cleared 7/15/2020 MIGUEL GAMBOA
Address approval Cleared 7/20/2020 GUILLERMO PETRA
Sewer availability Cleared 7/20/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 7/22/2020 GUILLERMO PETRA
Hydrant and Access approval Cleared 8/10/2020 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/5/2021 Approved VINCENT HANLEY
PLUMBING-Rough 4/30/2021 Partial Approval VINCENT HANLEY
Sewer 4/30/2021 Approved VINCENT HANLEY
Footing/Foundation/Slab 5/7/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 6/1/2021 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/1/2021 Approved VINCENT HANLEY
PLUMBING-Rough 6/1/2021 Partial Approval VINCENT HANLEY
Wood Frame 6/1/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 10/7/2021 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 10/7/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/7/2021 Approved VINCENT HANLEY
PLUMBING-Rough 10/7/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 10/13/2021 No Access for Inspection VINCENT HANLEY
Wood Frame 10/13/2021 No Access for Inspection VINCENT HANLEY
Pre-Inspection 11/12/2021 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 12/14/2021 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 12/14/2021 Corrections Issued VINCENT HANLEY
Pre-Inspection 12/14/2021 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 1/31/2022 Corrections Issued HENRY KIM
ELECTRICAL-Rough 2/7/2022 Not Ready for Inspection VINCENT HANLEY
Rough-Elec/Plmb/HVAC 2/28/2022 Approved VINCENT HANLEY
Insulation 3/3/2022 Approved VINCENT HANLEY
Drywall Nailing 3/10/2022 Approved MORRIS JACKSON
Shower Pan 3/10/2022 Approved MORRIS JACKSON
BUILDING-Rough-Frame 6/17/2022 Approved JEFFREY BULL
Final 6/17/2022 Corrections Issued JEFFREY BULL
Green Building Final 6/17/2022 Approved JEFFREY BULL
Green Building Rough 6/17/2022 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 6/17/2022 SGSOV Not Required JEFFREY BULL
Smoke Detectors 6/17/2022 Approved JEFFREY BULL
ELECTRICAL-Final 7/11/2022 Approved JEFFREY BULL
Final 7/11/2022 OK to Issue CofO JEFFREY BULL