13744 W ALBERS ST 91401
Certificate Information: 13744 W ALBERS ST 91401
- Application / Permit
- 20016-20000-10879
- Plan Check / Job No.
- B20VN06297
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 23' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 7/9/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/26/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2020 | RAPHAEL ROSAS |
| Corrections Issued | 5/12/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 6/23/2020 | ARTIN ZARUKIAN |
| Issued | 7/9/2020 | APPLICANT |
| CofO in Progress | 11/25/2020 | MICHAEL TEMPLE |
| CofO Issued | 12/26/2020 | MICHAEL SMITH |
| Permit Finaled | 12/26/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/19/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 5/19/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 5/19/2020 | JOHN TRIANTAFYLLOS |
| Certificate of Compliance | Cleared | 6/15/2020 | MIGUEL GAMBOA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/17/2020 | Partial Approval | MISAEL ESPARZA |
| Underground Mechanical | 7/17/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 7/22/2020 | Approved | WILLIAM KUEHN |
| Sewer | 7/22/2020 | Approved | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 7/31/2020 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 7/31/2020 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2020 | Partial Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 7/31/2020 | Approved | WILLIAM KUEHN |
| Underground Mechanical | 7/31/2020 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2020 | Partial Inspection | WILLIAM KUEHN |
| Interior/Exterior Lathing | 8/7/2020 | Partial Inspection | WILLIAM KUEHN |
| Insulation | 8/11/2020 | Approved | WILLIAM KUEHN |
| Shower Pan | 8/11/2020 | Approved | WILLIAM KUEHN |
| Drywall Nailing | 8/17/2020 | Approved | MICHAEL TEMPLE |
| Special/Order Compliance | 8/17/2020 | Corrections Issued | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 8/26/2020 | Approved | WILLIAM KUEHN |
| Service/Power Release | 8/26/2020 | Approved | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 9/24/2020 | Approved | WILLIAM KUEHN |
| Final | 9/24/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Green Building Final | 9/24/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Green Building Rough | 9/24/2020 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 9/24/2020 | SGSOV Approved | WILLIAM KUEHN |
| Smoke Detectors | 9/24/2020 | Approved | WILLIAM KUEHN |
| Final | 11/24/2020 | OK to Issue CofO | MICHAEL TEMPLE |
| Green Building Final | 11/24/2020 | Approved | MICHAEL TEMPLE |