2921 N GLENEDEN ST 90039
Certificate Information: 2921 N GLENEDEN ST 90039
- Application / Permit
- 20016-20000-10779
- Plan Check / Job No.
- B20VN06250
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 7/10/2020
- Issuing Office
- Current Status
- CofO Issued on 12/16/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2020 | JENNIFER LEE |
| Corrections Issued | 5/12/2020 | JENNIFER LEE |
| Applicant returned to address corrections | 6/4/2020 | ROSENDO MEDINA |
| Applicant returned to address corrections | 6/30/2020 | ROSENDO MEDINA |
| Plan Check Approved | 7/1/2020 | ROSENDO MEDINA |
| Issued | 7/10/2020 | APPLICANT |
| Building Plans Picked Up | 7/14/2020 | APPLICANT |
| CofO in Progress | 12/14/2020 | KATHRYN BUTTERWORTH |
| Permit Finaled | 12/16/2020 | DEROLD HAUFF |
| CofO Issued | 12/16/2020 | DEROLD HAUFF |
| Permit Finaled | 12/16/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/26/2020 | ELAINE LEI |
| Sewer availability | Cleared | 5/26/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 5/27/2020 | ELAINE LEI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/11/2020 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 9/17/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Rough-Elec/Plmb/HVAC | 9/17/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 9/23/2020 | No Access for Inspection | ELMER BLAND |
| ELECTRICAL-Rough | 9/24/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 9/24/2020 | Corrections Issued | ARTHUR SARGSYAN |
| HVAC-Rough | 9/24/2020 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 9/24/2020 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 10/5/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Drywall Nailing | 10/5/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 10/5/2020 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 10/5/2020 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 10/5/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 10/5/2020 | Approved | CRAIG VAUGHAN |
| MERV13>=Rough | 10/5/2020 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 10/5/2020 | SGSOV Not Ready | CRAIG VAUGHAN |
| Sewer | 10/5/2020 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 10/5/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 10/9/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 10/9/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Gas Test | 10/9/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 10/14/2020 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 10/15/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Drywall Nailing | 10/15/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 10/15/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 10/15/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 10/15/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Gas Test | 10/15/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Final | 10/15/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Final | 10/15/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 10/15/2020 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Smoke Detectors | 10/15/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Gas Test | 10/20/2020 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 10/20/2020 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Smoke Detectors | 10/20/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Underground Mechanical | 10/20/2020 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 10/26/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 11/4/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 11/16/2020 | Conditional Approval | DAVID CHAN |
| BUILDING-Rough-Frame | 11/17/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 11/18/2020 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 11/18/2020 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 11/24/2020 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 11/24/2020 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Shower Pan | 11/24/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Shower Pan | 12/2/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 12/3/2020 | Approved | KATHRYN BUTTERWORTH |
| Shower Pan | 12/3/2020 | Approved | KATHRYN BUTTERWORTH |
| Final | 12/8/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Final | 12/8/2020 | Approved | KATHRYN BUTTERWORTH |
| MERV13>=Final | 12/8/2020 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 12/8/2020 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Smoke Detectors | 12/8/2020 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 12/14/2020 | Approved | KATHRYN BUTTERWORTH |
| Final | 12/14/2020 | OK to Issue CofO | KATHRYN BUTTERWORTH |
| HVAC-Final | 12/14/2020 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 12/14/2020 | Approved | KATHRYN BUTTERWORTH |