11213 N MCLENNAN AVE 91344
Certificate Information: 11213 N MCLENNAN AVE 91344
- Application / Permit
- 20016-20000-10613
- Plan Check / Job No.
- B20VN06180
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED EXT/INT REMODEL - REMOVE WALLS BETWEEN KITCHEN/DINING/LIVING/DEN TO CREATE OPEN COMBINED KITCHEN/DINING/LIVING/DEN. REMODEL KITCHEN. RAISE FLR WITHIN DEN TO MATCH FLR ELEV OF OTHER RMS. CONVERT EX STORAGE RM INTO BATHRM & BEDRM. ENLARGE EX BATHRM. REPLACE EX WINDOWS W/ DIFF SIZE & CLOSE UP EX DOORS PER PLAN.
- Permit Issued
- Issued on 7/6/2020
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 10/29/2020
Permit Application Status History
| Submitted | 4/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 5/5/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 5/15/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 6/10/2020 | ALFRED RAMIREZ |
| Issued | 7/6/2020 | APPLICANT |
| Permit Finaled | 10/28/2020 | DAVID SCANTLIN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/8/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 5/8/2020 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 5/28/2020 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moradian,, Helbert; Lic. No.: C76618 | 6944 BECKETT STREET TUJUNGA, CA 91042 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/8/2020 | Conditional Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 7/10/2020 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 7/10/2020 | SGSOV Not Ready | DAVID SCANTLIN |
| Smoke Detectors | 7/10/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Footing/Foundation/Slab | 7/17/2020 | Approved | JOSEPH SAGEN |
| Underground Mechanical | 7/17/2020 | Approved | JOSEPH SAGEN |
| BUILDING-Rough-Frame | 8/3/2020 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 8/3/2020 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 8/3/2020 | Approved | DAVID SCANTLIN |
| Insulation | 8/10/2020 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 8/10/2020 | Partial Approval | DAVID SCANTLIN |
| Drywall Nailing | 8/14/2020 | Approved | DAVID SCANTLIN |
| Shower Pan | 8/25/2020 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 9/4/2020 | Approved | DAVID SCANTLIN |
| Final | 10/28/2020 | Permit Finaled | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 10/28/2020 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 10/28/2020 | Approved | DAVID SCANTLIN |