8107 N MAMMOTH AVE 91402
Certificate Information: 8107 N MAMMOTH AVE 91402
- Application / Permit
- 20016-20000-10543
- Plan Check / Job No.
- B20VN06141
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE INTO (N) ACCESSORY DWELLING UNIT PER WFPP W/O ADDITION. SEE COMMENTS.
- Permit Issued
- Issued on 9/3/2020
- Issuing Office
- Current Status
- CofO Issued on 4/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 5/19/2020 | NILOOFAR MEHRAIN |
| Building Plans Picked Up | 5/26/2020 | APPLICANT |
| Applicant returned to address corrections | 8/5/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 8/18/2020 | RAPHAEL ROSAS |
| Issued | 9/3/2020 | APPLICANT |
| CofO in Progress | 4/12/2023 | GREGG CUMMINGS |
| CofO Issued | 4/12/2023 | MICHAEL SMITH |
| Permit Finaled | 4/12/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/2/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 6/2/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 7/22/2020 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/18/2022 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 10/18/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Footing/Foundation/Slab | 11/9/2022 | Partial Approval | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 11/15/2022 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 11/18/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 11/18/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 11/18/2022 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/9/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/9/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 12/9/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 12/9/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 12/9/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/29/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/29/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 12/29/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 12/29/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/17/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 1/17/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 1/17/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 1/17/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 1/17/2023 | Approved | GREGG CUMMINGS |
| Sewer | 1/17/2023 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 1/17/2023 | Approved | GREGG CUMMINGS |
| Insulation | 1/20/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 1/26/2023 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 1/26/2023 | Approved | GREGG CUMMINGS |
| Insulation | 1/26/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 3/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 3/7/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 3/7/2023 | Approved | GREGG CUMMINGS |
| HVAC-Final | 3/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 3/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 3/7/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 3/7/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 4/3/2023 | Approved | GREGG CUMMINGS |
| Final | 4/3/2023 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 4/3/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 4/3/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 4/3/2023 | SGSOV Approved | GREGG CUMMINGS |