15801-15803 W COMMUNITY ST 91343

Certificate Information: 15801-15803 W COMMUNITY ST 91343

Application / Permit
20016-20000-10490
Plan Check / Job No.
B20VN06101
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 19'6"X20'0" ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER ENGR DESIGN. "COMPLY WITH DEPARTMENT ORDER effective date 04/18/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 9/29/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2020 APPLICANT
Assigned to Plan Check Engineer 5/6/2020 MARVEL DELACRUZ
Corrections Issued 5/12/2020 MARVEL DELACRUZ
Building Plans Picked Up 5/14/2020 APPLICANT
Applicant returned to address corrections 6/26/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 8/20/2020 JENNIFER LEE
Plan Check Approved 9/11/2020 RARES BODEA
Issued 9/29/2020 APPLICANT
CofO in Progress 2/17/2021 MARK DOVICO
Permit Finaled 2/24/2021 DAVID JAMES
CofO Issued 2/24/2021 DAVID JAMES
Permit Finaled 2/24/2021 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 5/26/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 5/26/2020 GABRIEL ROBLES
Sewer availability Cleared 5/26/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
FELIPE PENICHE, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/6/2020 Corrections Issued MARK DOVICO
Pre-Inspection 10/8/2020 Corrections Issued MARK DOVICO
Footing/Foundation/Slab 11/9/2020 Corrections Issued MARK DOVICO
Rough-Elec/Plmb/HVAC 11/17/2020 Corrections Issued MARK DOVICO
BUILDING-Rough-Frame 11/24/2020 Corrections Issued HAGOP BADOSSIAN
Green Building Rough 11/24/2020 Not Ready for Inspection HAGOP BADOSSIAN
PLUMBING-Rough 1/28/2021 Approved MARK DOVICO
BUILDING-Rough-Frame 2/10/2021 No Access for Inspection MARK DOVICO
Drywall Nailing 2/10/2021 No Access for Inspection MARK DOVICO
Final 2/10/2021 No Access for Inspection MARK DOVICO
Green Building Final 2/10/2021 No Access for Inspection MARK DOVICO
Green Building Rough 2/10/2021 No Access for Inspection MARK DOVICO
MERV13>=Final 2/10/2021 No Access for Inspection MARK DOVICO
MERV13>=Rough 2/10/2021 No Access for Inspection MARK DOVICO
SGSOV-Seismic Gas S/O Valve 2/10/2021 No Access for Inspection MARK DOVICO
Smoke Detectors 2/10/2021 No Access for Inspection MARK DOVICO
BUILDING-Rough-Frame 2/16/2021 Approved MARK DOVICO
Drywall Nailing 2/16/2021 Approved MARK DOVICO
Final 2/16/2021 Conditional Approval MARK DOVICO
Green Building Final 2/16/2021 Approved MARK DOVICO
Green Building Rough 2/16/2021 Approved MARK DOVICO
MERV13>=Final 2/16/2021 Approved MARK DOVICO
MERV13>=Rough 2/16/2021 Approved MARK DOVICO
SGSOV-Seismic Gas S/O Valve 2/16/2021 SGSOV Approved MARK DOVICO
Smoke Detectors 2/16/2021 Approved MARK DOVICO