454 N RUSTIC DR 90065

Certificate Information: 454 N RUSTIC DR 90065

Application / Permit
20016-20000-10475
Plan Check / Job No.
B20VN06091
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' X 31' RECREATION ROOM TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A); (E) ATTACHED GARAGE TO REMAIN. ALL WORK PER WFPP. [FIRE SPRINKLERS REQUIRED THROUGHOUT]
Permit Issued
Issued on 10/29/2020
Issuing Office
Current Status
Issued on 10/29/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/29/2020 APPLICANT
Assigned to Plan Check Engineer 5/6/2020 SEAN SHAHMIRI
Corrections Issued 5/11/2020 SEAN SHAHMIRI
Building Plans Picked Up 5/14/2020 APPLICANT
Applicant returned to address corrections 8/10/2020 JENNIFER LEE
Plan Check Approved 9/3/2020 JENNIFER LEE
Issued 10/29/2020 APPLICANT

Permit Application Clearance Information

Miscellaneous Cleared 5/28/2020 RUBEN VASQUEZ
ZA Case Cleared 5/28/2020 RUBEN VASQUEZ
ZA Case Cleared 5/28/2020 RUBEN VASQUEZ
Address approval Cleared 6/16/2020 CELINA MORENO
Sewer availability Cleared 6/16/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 6/18/2020 CELINA MORENO
Specific Plan Cleared 7/21/2020 DYLAN LAWRENCE

Contact Information

Contractor Igreen Remodeling Inc; Lic. No.: 1047582-B 8549 WILSHIRE BLVD #1263      BEVERLY HILLS, CA 90211

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 1/8/2021 Corrections Issued RUBEN SALAS
HVAC-Rough 1/8/2021 Corrections Issued RUBEN SALAS
PLUMBING-Rough 1/8/2021 Partial Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/15/2021 Not Ready for Inspection RUBEN SALAS
HVAC-Rough 1/15/2021 Not Ready for Inspection RUBEN SALAS
PLUMBING-Rough 1/15/2021 Corrections Issued RUBEN SALAS
ELECTRICAL-Rough 1/26/2021 Not Ready for Inspection OSVALDO PARAMO
HVAC-Rough 1/26/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 1/26/2021 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 2/9/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 2/9/2021 Approved OSVALDO PARAMO
Shower Pan 2/24/2021 Approved OSVALDO PARAMO
Drywall Nailing 3/2/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 3/2/2021 Partial Approval OSVALDO PARAMO
Final 9/30/2025 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Final 9/30/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 9/30/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 9/30/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 11/21/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 11/21/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 11/21/2025 Not Ready for Inspection ALIZAH MAYAGOITIA