454 N RUSTIC DR 90065
Certificate Information: 454 N RUSTIC DR 90065
- Application / Permit
- 20016-20000-10475
- Plan Check / Job No.
- B20VN06091
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 31' RECREATION ROOM TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A); (E) ATTACHED GARAGE TO REMAIN. ALL WORK PER WFPP. [FIRE SPRINKLERS REQUIRED THROUGHOUT]
- Permit Issued
- Issued on 10/29/2020
- Issuing Office
- Current Status
- Issued on 10/29/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2020 | SEAN SHAHMIRI |
| Corrections Issued | 5/11/2020 | SEAN SHAHMIRI |
| Building Plans Picked Up | 5/14/2020 | APPLICANT |
| Applicant returned to address corrections | 8/10/2020 | JENNIFER LEE |
| Plan Check Approved | 9/3/2020 | JENNIFER LEE |
| Issued | 10/29/2020 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 5/28/2020 | RUBEN VASQUEZ |
| ZA Case | Cleared | 5/28/2020 | RUBEN VASQUEZ |
| ZA Case | Cleared | 5/28/2020 | RUBEN VASQUEZ |
| Address approval | Cleared | 6/16/2020 | CELINA MORENO |
| Sewer availability | Cleared | 6/16/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2020 | CELINA MORENO |
| Specific Plan | Cleared | 7/21/2020 | DYLAN LAWRENCE |
Contact Information
| Contractor | Igreen Remodeling Inc; Lic. No.: 1047582-B | 8549 WILSHIRE BLVD #1263 BEVERLY HILLS, CA 90211 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 1/8/2021 | Corrections Issued | RUBEN SALAS |
| HVAC-Rough | 1/8/2021 | Corrections Issued | RUBEN SALAS |
| PLUMBING-Rough | 1/8/2021 | Partial Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 1/15/2021 | Not Ready for Inspection | RUBEN SALAS |
| HVAC-Rough | 1/15/2021 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 1/15/2021 | Corrections Issued | RUBEN SALAS |
| ELECTRICAL-Rough | 1/26/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| HVAC-Rough | 1/26/2021 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 1/26/2021 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 2/9/2021 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 2/9/2021 | Approved | OSVALDO PARAMO |
| Shower Pan | 2/24/2021 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 3/2/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 3/2/2021 | Partial Approval | OSVALDO PARAMO |
| Final | 9/30/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Final | 9/30/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 9/30/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 9/30/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 11/21/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 11/21/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 11/21/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |