6532 N COMANCHE AVE 91306
Certificate Information: 6532 N COMANCHE AVE 91306
- Application / Permit
- 20016-20000-10464
- Plan Check / Job No.
- B20VN06085
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 20' DETACHED 2-CAR GARAGE TO ADU. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 1/20/2021
- Issuing Office
- Current Status
- CofO Issued on 9/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 6/21/2020 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 7/7/2020 | APPLICANT |
| Plan Check Approved | 11/16/2020 | GURUNATH NESARAJAH |
| Issued | 1/20/2021 | APPLICANT |
| CofO in Progress | 9/9/2024 | ALEXANDER HANDY |
| Permit Finaled | 9/27/2024 | JOHN JANSON |
| CofO Issued | 9/27/2024 | JOHN JANSON |
| Permit Finaled | 9/27/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 10/21/2020 | ADRIAN CASTRO |
| ZI | Cleared | 11/16/2020 | MIGUEL GAMBOA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 2/4/2021 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 2/4/2021 | Not Ready for Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 2/8/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 2/8/2021 | Corrections Issued | HENRY KIM |
| Sewer | 2/8/2021 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 5/18/2021 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 5/18/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 5/18/2021 | Corrections Issued | HENRY KIM |
| Underground Mechanical | 5/18/2021 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Final | 7/1/2021 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 7/1/2021 | Corrections Issued | HENRY KIM |
| Deputy Drilled-In Anchors | 7/22/2021 | Conditional Approval | ALIZAH MAYAGOITIA |
| Deputy Other (see comments) | 7/22/2021 | Conditional Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/9/2021 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 8/9/2021 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 11/30/2021 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 11/30/2021 | Partial Approval | STEVEN BACK |
| Underground Mechanical | 11/30/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2022 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 2/28/2022 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 3/10/2022 | Approved | STEVEN BACK |
| Deputy Drilled-In Anchors | 3/15/2022 | Conditional Approval | STEVEN BACK |
| Insulation | 4/18/2022 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 4/18/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/18/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2022 | Approved | STEVEN BACK |
| Insulation | 5/18/2022 | Approved | STEVEN BACK |
| Drywall Nailing | 6/28/2022 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 6/28/2022 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 12/20/2022 | Approved | SEAN HAUPT |
| Final | 12/20/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 12/20/2022 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 12/20/2022 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 12/20/2022 | SGSOV Not Ready | SEAN HAUPT |
| Smoke Detectors | 12/20/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 3/23/2023 | Approved | ALEXANDER HANDY |
| Final | 3/23/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 3/23/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Rough | 3/23/2023 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 3/23/2023 | SGSOV Approved | ALEXANDER HANDY |
| Final | 8/27/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 8/27/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Final | 9/6/2024 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 9/6/2024 | Approved | ALEXANDER HANDY |