6532 N COMANCHE AVE 91306

Certificate Information: 6532 N COMANCHE AVE 91306

Application / Permit
20016-20000-10464
Plan Check / Job No.
B20VN06085
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' X 20' DETACHED 2-CAR GARAGE TO ADU. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 1/20/2021
Issuing Office
Current Status
CofO Issued on 9/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2020 APPLICANT
Assigned to Plan Check Engineer 6/21/2020 GURUNATH NESARAJAH
Corrections Issued 6/21/2020 GURUNATH NESARAJAH
Building Plans Picked Up 7/7/2020 APPLICANT
Plan Check Approved 11/16/2020 GURUNATH NESARAJAH
Issued 1/20/2021 APPLICANT
CofO in Progress 9/9/2024 ALEXANDER HANDY
Permit Finaled 9/27/2024 JOHN JANSON
CofO Issued 9/27/2024 JOHN JANSON
Permit Finaled 9/27/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/21/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/21/2020 ADRIAN CASTRO
Sewer availability Cleared 10/21/2020 ADRIAN CASTRO
ZI Cleared 11/16/2020 MIGUEL GAMBOA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 2/4/2021 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 2/4/2021 Not Ready for Inspection HENRY KIM
BUILDING-Rough-Frame 2/8/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 2/8/2021 Corrections Issued HENRY KIM
Sewer 2/8/2021 Approved HENRY KIM
BUILDING-Rough-Frame 5/18/2021 Corrections Issued HENRY KIM
Footing/Foundation/Slab 5/18/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 5/18/2021 Corrections Issued HENRY KIM
Underground Mechanical 5/18/2021 Corrections Issued HENRY KIM
ELECTRICAL-Final 7/1/2021 Corrections Issued HENRY KIM
Footing/Foundation/Slab 7/1/2021 Corrections Issued HENRY KIM
Deputy Drilled-In Anchors 7/22/2021 Conditional Approval ALIZAH MAYAGOITIA
Deputy Other (see comments) 7/22/2021 Conditional Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 8/9/2021 Approved JEFFREY PARD
PLUMBING-Rough 8/9/2021 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 11/30/2021 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 11/30/2021 Partial Approval STEVEN BACK
Underground Mechanical 11/30/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 2/28/2022 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 2/28/2022 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 3/10/2022 Approved STEVEN BACK
Deputy Drilled-In Anchors 3/15/2022 Conditional Approval STEVEN BACK
Insulation 4/18/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 4/18/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 5/18/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/18/2022 Approved STEVEN BACK
Insulation 5/18/2022 Approved STEVEN BACK
Drywall Nailing 6/28/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 6/28/2022 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 12/20/2022 Approved SEAN HAUPT
Final 12/20/2022 Corrections Issued SEAN HAUPT
Green Building Final 12/20/2022 Not Ready for Inspection SEAN HAUPT
Green Building Rough 12/20/2022 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 12/20/2022 SGSOV Not Ready SEAN HAUPT
Smoke Detectors 12/20/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 3/23/2023 Approved ALEXANDER HANDY
Final 3/23/2023 Not Ready for Inspection ALEXANDER HANDY
Green Building Final 3/23/2023 Not Ready for Inspection ALEXANDER HANDY
Green Building Rough 3/23/2023 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 3/23/2023 SGSOV Approved ALEXANDER HANDY
Final 8/27/2024 Not Ready for Inspection ALEXANDER HANDY
Green Building Final 8/27/2024 Not Ready for Inspection ALEXANDER HANDY
Final 9/6/2024 OK to Issue CofO ALEXANDER HANDY
Green Building Final 9/6/2024 Approved ALEXANDER HANDY