12883 N NORRIS AVE 91342

Certificate Information: 12883 N NORRIS AVE 91342

Application / Permit
20016-20000-10461
Plan Check / Job No.
B20VN06083
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED CARPORT INTO ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 7/16/2020
Issuing Office
Current Status
CofO Issued on 2/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2020 APPLICANT
Assigned to Plan Check Engineer 5/4/2020 LUIS RINCON
Corrections Issued 5/6/2020 LUIS RINCON
Plan Check Approved 7/6/2020 JEROME MAGAT PALMA
Issued 7/16/2020 APPLICANT
Building Plans Picked Up 7/17/2020 APPLICANT
CofO in Progress 1/8/2021 MISAEL ESPARZA
Permit Finaled 2/13/2021 MICHAEL SMITH
CofO Issued 2/13/2021 MICHAEL SMITH
Permit Finaled 2/13/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/18/2020 ADRIAN CASTRO
Sewer availability Cleared 5/18/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/19/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 6/17/2020 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Gosen,, James W; Lic. No.: C43590 15315 BLEDSOE ST      SYLMAR, CA 91342

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/3/2020 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 8/3/2020 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 8/4/2020 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 8/6/2020 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 9/8/2020 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 9/8/2020 Approved MISAEL ESPARZA
Green Building Rough 9/8/2020 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 9/8/2020 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 9/8/2020 Approved MISAEL ESPARZA
Sewer 9/8/2020 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 9/15/2020 Approved MISAEL ESPARZA
Green Building Rough 9/15/2020 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 9/15/2020 Approved MISAEL ESPARZA
Insulation 9/18/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 9/18/2020 Partial Approval MISAEL ESPARZA
Drywall Nailing 9/23/2020 Approved MISAEL ESPARZA
Green Building Rough 9/23/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 9/23/2020 Approved MISAEL ESPARZA
Final 10/28/2020 Corrections Issued MISAEL ESPARZA
Green Building Final 10/28/2020 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 10/28/2020 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 10/28/2020 Approved MISAEL ESPARZA
Final 11/19/2020 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 11/19/2020 Approved MISAEL ESPARZA
HVAC-Final 11/19/2020 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 11/19/2020 SGSOV Not Ready MISAEL ESPARZA
Final 12/23/2020 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 12/23/2020 SGSOV Not Ready MISAEL ESPARZA
ELECTRICAL-Final 1/7/2021 Approved MISAEL ESPARZA
Final 1/7/2021 OK to Issue CofO MISAEL ESPARZA
HVAC-Final 1/7/2021 Approved MISAEL ESPARZA
PLUMBING-Final 1/7/2021 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 1/7/2021 SGSOV Approved MISAEL ESPARZA