14880 W JADESTONE DR 91403
Certificate Information: 14880 W JADESTONE DR 91403
- Application / Permit
- 20016-20000-10442
- Plan Check / Job No.
- B20VN06064
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSE 8'-1" -7' IRREGULAR SHAPED FRONT PORCH AND INTERIOR REMODEL TO EXPAND BATHROOM, ADD NEW LAUNDRY ROOM AND BATHROOM ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/4/2020
- Issuing Office
- Current Status
- CofO Issued on 12/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 5/14/2020 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 5/15/2020 | APPLICANT |
| Plan Check Approved | 10/19/2020 | MANUEL GARCIA |
| Issued | 11/4/2020 | APPLICANT |
| CofO in Progress | 4/7/2021 | CHARLES POWELL |
| CofO in Progress | 4/7/2021 | CHARLES POWELL |
| Permit Finaled | 12/18/2021 | MICHAEL SMITH |
| CofO Issued | 12/18/2021 | MICHAEL SMITH |
| Permit Finaled | 12/18/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 5/26/2020 | MIGUEL GAMBOA |
| Sewer availability | Cleared | 5/26/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/27/2020 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 7/23/2020 | PATRICK MISCHLICH |
| Specific Plan | Cleared | 10/8/2020 | TRACY WILLIAMS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/9/2020 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 11/16/2020 | Not Ready for Inspection | CHARLES POWELL |
| ELECTRICAL-Rough | 11/16/2020 | Not Ready for Inspection | CHARLES POWELL |
| Green Building Rough | 11/16/2020 | Not Ready for Inspection | CHARLES POWELL |
| PLUMBING-Rough | 11/16/2020 | Not Ready for Inspection | CHARLES POWELL |
| ELECTRICAL-Rough | 11/18/2020 | Corrections Issued | CHARLES POWELL |
| PLUMBING-Rough | 11/18/2020 | Corrections Issued | CHARLES POWELL |
| BUILDING-Rough-Frame | 11/23/2020 | Approved | CHARLES POWELL |
| ELECTRICAL-Rough | 11/23/2020 | Partial Approval | CHARLES POWELL |
| Green Building Rough | 11/23/2020 | Not Ready for Inspection | CHARLES POWELL |
| PLUMBING-Rough | 11/23/2020 | Not Ready for Inspection | CHARLES POWELL |
| Insulation | 11/25/2020 | Approved | CHARLES POWELL |
| Interior/Exterior Lathing | 11/25/2020 | Approved | CHARLES POWELL |
| Drywall Nailing | 12/1/2020 | Approved | CHARLES POWELL |
| Green Building Rough | 12/1/2020 | Approved | CHARLES POWELL |
| Final | 3/23/2021 | Corrections Issued | CHARLES POWELL |
| Green Building Final | 3/23/2021 | Approved | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 3/23/2021 | SGSOV Not Ready | CHARLES POWELL |
| Smoke Detectors | 3/23/2021 | Approved | CHARLES POWELL |
| Final | 4/6/2021 | OK to Issue CofO | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 4/6/2021 | SGSOV Approved | CHARLES POWELL |