14880 W JADESTONE DR 91403

Certificate Information: 14880 W JADESTONE DR 91403

Application / Permit
20016-20000-10442
Plan Check / Job No.
B20VN06064
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSE 8'-1" -7' IRREGULAR SHAPED FRONT PORCH AND INTERIOR REMODEL TO EXPAND BATHROOM, ADD NEW LAUNDRY ROOM AND BATHROOM ALL WORK PER ENGINEERING
Permit Issued
Issued on 11/4/2020
Issuing Office
Current Status
CofO Issued on 12/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2020 APPLICANT
Assigned to Plan Check Engineer 5/7/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 5/14/2020 SEWADA ZADOORIAN MILAGARDI
Building Plans Picked Up 5/15/2020 APPLICANT
Plan Check Approved 10/19/2020 MANUEL GARCIA
Issued 11/4/2020 APPLICANT
CofO in Progress 4/7/2021 CHARLES POWELL
CofO in Progress 4/7/2021 CHARLES POWELL
Permit Finaled 12/18/2021 MICHAEL SMITH
CofO Issued 12/18/2021 MICHAEL SMITH
Permit Finaled 12/18/2021 MICHAEL SMITH

Permit Application Clearance Information

Miscellaneous Cleared 5/26/2020 MIGUEL GAMBOA
Sewer availability Cleared 5/26/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 5/27/2020 GABRIEL ROBLES
Grading Pre-Inspection Cleared 7/23/2020 PATRICK MISCHLICH
Specific Plan Cleared 10/8/2020 TRACY WILLIAMS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/9/2020 Approved CHARLES POWELL
BUILDING-Rough-Frame 11/16/2020 Not Ready for Inspection CHARLES POWELL
ELECTRICAL-Rough 11/16/2020 Not Ready for Inspection CHARLES POWELL
Green Building Rough 11/16/2020 Not Ready for Inspection CHARLES POWELL
PLUMBING-Rough 11/16/2020 Not Ready for Inspection CHARLES POWELL
ELECTRICAL-Rough 11/18/2020 Corrections Issued CHARLES POWELL
PLUMBING-Rough 11/18/2020 Corrections Issued CHARLES POWELL
BUILDING-Rough-Frame 11/23/2020 Approved CHARLES POWELL
ELECTRICAL-Rough 11/23/2020 Partial Approval CHARLES POWELL
Green Building Rough 11/23/2020 Not Ready for Inspection CHARLES POWELL
PLUMBING-Rough 11/23/2020 Not Ready for Inspection CHARLES POWELL
Insulation 11/25/2020 Approved CHARLES POWELL
Interior/Exterior Lathing 11/25/2020 Approved CHARLES POWELL
Drywall Nailing 12/1/2020 Approved CHARLES POWELL
Green Building Rough 12/1/2020 Approved CHARLES POWELL
Final 3/23/2021 Corrections Issued CHARLES POWELL
Green Building Final 3/23/2021 Approved CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 3/23/2021 SGSOV Not Ready CHARLES POWELL
Smoke Detectors 3/23/2021 Approved CHARLES POWELL
Final 4/6/2021 OK to Issue CofO CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 4/6/2021 SGSOV Approved CHARLES POWELL