10357 W ROSCOE BLVD 91352

Certificate Information: 10357 W ROSCOE BLVD 91352

Application / Permit
20016-20000-10392
Plan Check / Job No.
B20VN06042
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 20'4" x 18'4" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 7/24/2020
Issuing Office
Metro
Current Status
CofO Issued on 5/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2020 APPLICANT
Assigned to Plan Check Engineer 5/6/2020 JEFFREY TANGONAN
Plan Check Approved 6/11/2020 GURUNATH NESARAJAH
Issued 7/24/2020 APPLICANT
CofO in Progress 3/8/2021 BEAU COLLINS
CofO Issued 5/22/2021 MICHAEL SMITH
Permit Finaled 5/22/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/13/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/13/2020 ADRIAN CASTRO
Sewer availability Cleared 5/13/2020 ADRIAN CASTRO
Street Frontage Cleared 5/13/2020 ADRIAN CASTRO
Grading Pre-Inspection Cleared 6/3/2020 VASIL MIHALEV

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/5/2020 Partial Approval JOHN HAYES
PLUMBING-Rough 10/14/2020 Partial Approval BEAU COLLINS
Deputy Drilled-In Anchors 10/27/2020 Approved BEAU COLLINS
Footing/Foundation/Slab 10/28/2020 Approved BEAU COLLINS
PLUMBING-Rough 10/28/2020 Partial Approval BEAU COLLINS
BUILDING-Rough-Frame 11/10/2020 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 11/10/2020 Not Ready for Inspection JOHN HAYES
Green Building Rough 11/10/2020 Not Ready for Inspection JOHN HAYES
HVAC-Rough 11/10/2020 Not Ready for Inspection JOHN HAYES
MERV13>=Rough 11/10/2020 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 11/19/2020 Approved BEAU COLLINS
HVAC-Rough 11/19/2020 Partial Inspection BEAU COLLINS
BUILDING-Rough-Frame 11/25/2020 Approved GREGG CUMMINGS
Insulation 11/25/2020 Approved GREGG CUMMINGS
Interior/Exterior Lathing 11/25/2020 Partial Approval GREGG CUMMINGS
MERV13>=Rough 11/25/2020 Approved GREGG CUMMINGS
Drywall Nailing 12/3/2020 Approved BEAU COLLINS
Green Building Rough 12/3/2020 Approved BEAU COLLINS
Shower Pan 12/15/2020 Approved BEAU COLLINS
Final 2/22/2021 Corrections Issued BEAU COLLINS
Green Building Final 2/22/2021 Not Ready for Inspection BEAU COLLINS
MERV13>=Final 2/22/2021 Approved BEAU COLLINS
SGSOV-Seismic Gas S/O Valve 2/22/2021 SGSOV Approved BEAU COLLINS
Smoke Detectors 2/22/2021 Approved BEAU COLLINS
Final 3/5/2021 OK to Issue CofO BEAU COLLINS
Green Building Final 3/5/2021 Approved BEAU COLLINS